| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrockrequiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete Earthwork Excavation |
| 2 | Supplying and filling with clear M- sand for foundation and basement including cost and conveyance of all charges etc., complete as per standard specifications |
| 3 | Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification |
| 4 | M-20 CONCRETE - Providing and laying in position, standarised design mix M-20 Grade using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 350Kg/m3 and maximum water cement ratio of 0.55, including admixture(plasticiser/super plasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability with about (5.70 cu.m.)940.50Kg of 20mm machine crushed stone jelly and with about (2.80 cu.m.)462.00Kg of 10-12mm machine crushed jelly and with about (4.25 cu.m.)701.25Kg of sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor/roof slabs wherever neccessary without clambing extra, etc. complete complying with standard specification and as directed by the departmental officers. the coarse and fine aggregates to be used should comply with the requierments of IS 383-2016. (No separate payment will be made by the department for the exces usage of materials as per design mix.) |
| 5 | Suppling and fabricating and placing in position MS(or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost ofsteel and binding wire also in all floors. |
| 6 | Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9\"X43/8\"X 2 3/4\" including finishing, curing, etc., complete complying with standard specification.- |
| 7 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) |
| 8 | Providing GI Sheet roofing using Galvanisediron color sheet of standard thickness of ISI standard including cost of materials and labour charges etc., complete as per standard specification |
| 9 | Providing Structural steel work using MS circular pipe / sq pipes including all cost etc., |