| 1 | Excavation foundation in hard soil including dressing and leveling the bed up to required level and depositing the excavated earh with initial lead and lift with cost of all labour etc., complete as per direction of the Engineer in charge |
| 2 | 1ST DEPTH. |
| 3 | 2ND DEPTH. |
| 4 | Providing plain cement concrete (1:3:6) using 4cmsize black hard granite crusher broken metal mixing concrete hoisting laying compacting centering and shuttering where required watering and curring with cost conveyance royalty taxes of all materials and cost of all labour required for the work etc., complete as per directio of the Egineer in charge. |
| 5 | 1ST DEPTH. |
| 6 | 2ND DEPTH. |
| 7 | Providing RCC M-20 grade using 20mm down graded balck hard granite crusher broken metal mixing concrete hoisting laying compacting centering and shuttering where required watering and curring with cost conveyance royalty taxes of all materials and cost of all labour required for the work etc., complete as per directio of the Engineer in charge. |
| 8 | Column Base / Footings |
| 9 | Grade Beam |
| 10 | Lintel (Ground Floor) |
| 11 | Lintel (1st Floor) |
| 12 | Chajja (Ground Floor) |
| 13 | Chajja (1st Floor) |
| 14 | Fin Wall (Ground Floor) |
| 15 | Fin Wall (1st Floor) |
| 16 | Stair Case (Ground Floor) |
| 17 | Stair Case (1st Floor) |
| 18 | Column S/S & Beam (Ground Floor) |
| 19 | Column S/S & Beam (1st Floor) |
| 20 | Column S/S & Beam (2nd Floor) |
| 21 | Roof Slab (Ground Floor) |
| 22 | Roof Slab (1st Floor) |
| 23 | Roof Slab (2nd Floor) |
| 24 | Providing supplying placing uncoated HYSD bar reinforcement as per drawing and technical specification including cutting bending binding and tying the grill placing in position as required for RCC work including cost of MS toor steel, binding wire cost coneyance taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge. |
| 25 | GROUND FLOOR |
| 26 | FIRST FLOOR |
| 27 | SECOND FLOOR |
| 28 | Fly Ash Brick masonry in CM (1:6) in all floor using the bricks after immersing six hours in water before use splays cutting circular moulding chafering watering curring with cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge |
| 29 | Foundation and Plinth |
| 30 | Superstructure (Ground Floor) |
| 31 | Superstructure (First Floor) |
| 32 | Superstructure (Second Floor) |
| 33 | Filling foundation and plinth with sand well watered and rammed including cost coneyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge |
| 34 | 12mm thick cement plaster in CM (1:6) finished smooth to brick wall after racking out the joinst watering curring with cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge |
| 35 | GROUND FLOOR |
| 36 | FIRST FLOOR |
| 37 | SECOND FLOOR |
| 38 | 16mm thick cement plaster in CM (1:6) fiished smooth to brick wall after racking out the joints watering curring with cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge. |
| 39 | GROUND FLOOR |
| 40 | FIRST FLOOR |
| 41 | SECOND FLOOR |
| 42 | 6mm thick cement plaster in CM (1:4) finished smooth to exposed surface of RCC work after deep chipping neat cement slurry watering curring with cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge. |
| 43 | GROUND FLOOR |
| 44 | FIRST FLOOR |
| 45 | SECOND FLOOR |
| 46 | Providing supplying fitting and fixing vitrified tiles in floor on 20mm thick bed in CM (1:3) joined with white cement mixed with pigment watering curring including cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge\ |
| 47 | GROUND FLOOR |
| 48 | FIRST FLOOR |
| 49 | Providing supplying fitting and fixing vitrified tile in wall on 12mm thick cement plaster in CM (1:3) jointed with neat cemet slurry mixed with pigment watering curring including cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of Engineer in charge. |
| 50 | GROUND FLOOR |
| 51 | FIRST FLOOR |
| 52 | Providing supplying fitting and fixing ceramic tile in floor on 20mm thick bed in CM (1:3) jointed with neat cement slurry mixed with pigment watering watering curring including cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the ENgineer in charge |
| 53 | GROUND FLOOR |
| 54 | FIRST FLOOR |
| 55 | Providing supplying fitting and fixing ceramic glazed tile in wall on 12mm thick cement plaster in CM (1:3) jointed with white cement mixed with pigment watering curring including cost conveyance royalty taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge |
| 56 | GROUND FLOOR |
| 57 | FIRST FLOOR |
| 58 | Providing supplying G.I. door iwndow grill and grill gate of approved design mae out of G.I. angle frame and G.I> sheet shutter including cost conveyance taxs of al materials and cost of all labour etc., complete as per direction of the Engineer in charge. |
| 59 | GROUND FLOOR |
| 60 | FIRST FLOOR |
| 61 | SECOND FLOOR |
| 62 | Labour charges for fitting ad fixing GI door window in position includingcost of all labour materials etc., complete as per directio of the Engineer in charge |
| 63 | GROUND FLOOR |
| 64 | FIRST FLOOR |
| 65 | SECOND FLOOR |
| 66 | Painting 2 coats to door window grill and grill gate with eamel paint of approved shade over a coat of red oxide primer after cleaning surface free from oil and grease sand papering polishing inclduing cost coveyance taxes of all materials and cost of all labour requried for the work etc., complete as per direction of the Engineer in charge. |
| 67 | GROUND FLOOR |
| 68 | FIRST FLOOR |
| 69 | SECOND FLOOR |
| 70 | Supplying fitting fixig of stainless stell of 304 grae in hand railling using 50n dia of 2mm thick circular pipe with balustrade of size 32mmx32mmx2mm in 3rows in stair case as per approved design and specification butting polishing etc., with cost conveyance taxes of all materials labour T&P etc., complete as per direction of the Engineer in charge. |
| 71 | GROUND FLOOR |
| 72 | FIRST FLOOR |
| 73 | Prime one coat over plaster surface with water bound cement primer to received paint after cleaning surface free from dust and extraneous materials with cost conveyance taxes of all materials and cost of all labour etc., complete as per Engineer in charge |
| 74 | GROUND FLOOR |
| 75 | FIRST FLOOR (OUT SIDE) |
| 76 | FIRST FLOOR (IN SIDE) |
| 77 | SECOND FLOOR (OUT SIDE) |
| 78 | SECOND FLOOR (IN SIDE) |
| 79 | Distemper 2 coats over plaster surface with approved shade of approved make after cleaniing surface free from dust and extraneous materials with cost conveyance taxes of all materials and cost of all labour etc., complete as direction of the Engineer in charge. |
| 80 | GROUND FLOOR |
| 81 | FIRST FLOOR |
| 82 | SECOND FLOOR |
| 83 | Wall painting with weather coat 2 coats over plaster surface with approved shade of approved make after cleaning surface free from dust and extraneous materials with cost conveyance taxes of all materials and cost of all labour etc., complete as per direction of the Engineer in charge. |
| 84 | GROUND FLOOR |
| 85 | FIRST FLOOR |
| 86 | SECOND FLOOR |