| 1 | 1 | Earth work in excavation by manual means over areas (Exceeding 30 cm and up to 1.5 Mtr. in depth,1.5mtr in width as well as 10 sqm on plan) including disposal of excavated earth upto1 Mtr. for cutting edge, disposed earth to be levelled and neatly dressed in | | | |
|---|
| 2 | 1.01 | All kind of soil | | 1735.39 | cum |
|---|
| 3 | 1.02 | Soft Rock | | 192.82 | cum |
|---|
| 4 | 2 | Earth work in excavation by manual means in trenches for foundation ,drains, pipes ,cables etc.(Not exceeding 1.5mtr in width ) and for shafts, wells, cesspits and the like not exceeding 10sqm on plan ,depth up to 1.5mtr including disposal of excavated earth up to 1mtr from cutting edge, disposed earth to be levelled and neatly dressed | | | |
|---|
| 5 | 2.01 | All kind of soil | | 218.97 | cum |
|---|
| 6 | 2.02 | Soft Rock | | 24.33 | cum |
|---|
| 7 | 3 | P/L soling with hard stone in foundation incl.cost of stone and carraige of stone for an avg. lead of 10Km by M.T | | 8.53 | cum |
|---|
| 8 | 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering -All work upto plinth level.1:3:6(1 cement :3 coarse sand ; 6graded stone aggregate 20mm nominal size. crushed incl. Carriage of sand /crushed agregade /cement & steel for an avg. lead of 85 Km by M.T | | 151.85 | cum |
|---|
| 9 | 5 | Reinforced cement concrete work in walls (any thickness) including attatched plasters butteress ,plinth and string courses ,filets ,columns,pillars ,piers,abbutments ,post and struts,etc. upto floor five level excluding cost of centring, shuttering,finishing and reinforcement 1:1.5:3(1 cement:1.5 course :3 graded crushed stone agregate 20mm nominal size) incl. all sorts of carriage as in item 4\n | | 38.67 | Cum |
|---|
| 10 | 6 | Providing and laying in position sepecified grade of reinforced cement concrete excluding the cost of centring and shuttering ,finishing,and reinforcement-All work upto Plinth level 1:1.5:3 (1 cement: 1.5 coarse sand: 3 graded stone aggregate 20mm nominal size. (crushed agregate)and all souce of carriage complete as item 4 | | 20.7 | cum |
|---|
| 11 | 7 | Reinforcement for R.C.C. work including straightening, cutting,bending placing in position and binding all complete.Hot rolled deformed bars & incl carriage of steel by an avg. lead of 45 km by MT &600mtr H/Load. | | 2090.76 | Kg |
|---|
| 12 | 8 | Centring and shuttering including strutting propping etc,and removal of form work for Walls (any thickness) incld. attached pilasters, buttresses, plinth & string courses etc.incl. form work for foundation/footingsof columns,pillars & suspended floor complete job as per direction of site Engineer | | 702.1 | sqm |
|---|
| 13 | 9 | Hydraulic structural design for the steel flume over RCC columns along with calculations and working drawing vetted from Design directorate / NIT srinagar complete job | | 1 | job |
|---|
| 14 | 10 | Supply/fabrication/ testing & commissioning of steel flume structure incl. cuting/welding and fixing above 7.00mtr head complete job as per direction of consultant/site Engineer incharge incl.priming and all sorts of carraiage | | 11000 | Kg |
|---|
| 15 | 11 | Dewatering from trenches during execution of work as per site requirement complete job | | 1 | job |
|---|
| 16 | 12 | Disposal of excavated earth /Mulba from site for an avg. lead of 2.00 Km by M.T | | 1303 | Cum |
|---|