| 1 | Excavating,supplying, stacking and filling of local earth (includingroyalty) by mechanical transport upto a lead of5kmalso includingramming andwatering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundationetc. complete for all lift. |
| 2 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller8 including making good the undulations etc. and re-rolling the subWC .g rade and disposal of surplus earthwith lead upto 50 metres. |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in- charge. |
| 4 | Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge. With material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBR Value-25 |
| 5 | M-150 brick work in one cement & four coarse sand 2.25 F.M. mortar in foundation and plinth including supply of all materials labour, tools and plants etc. required for proper completion of the work. |
| 6 | Providing and layingin cement concrete 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded Stone aggregate 20 mm nominal size) in road slab and curing complete, including cost ofform-work, in foundation and floors. |
| 7 | Providing and laying in position bitumen hot sealing compound for expansion joints etc. Using grade \"A\" sealing compound. |
| 8 | Excavation in foundation in ordinary soil (loam clay or sand) including lift upto 1.50 meter and lead upto 30 meter and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of sur-plus earth as directed by the Engineer incharge up to a distance of 30 meters from the foundation trenches. |
| 9 | Providing and laying in cement concrete 1:4:8 (1 cement : 4 coarse sand :8 graded Stone aggregate 40 mm nominal size) and curing complete,including cost of form- work, in foundation and floors. |
| 10 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). |
| 11 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
| 12 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 13 | P/F TMT Bar -Fe 500 in plain work such as reinforced concrete or reinforced, brick work (when not included in over all rates ) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorised over lapping shall be measured upto floor two level. |
| 14 | First class brick work in 1:6 cement and coarse sand of 2.25 fineness modulus) mortar infoundation & plinth including supply of all materials, labour and T & P etc reqiored for proper completion of the work. |
| 15 | M-150 Brick work in super structure in1:4 cement and coarse sand mortar in superstructure for wall thickness 12 cms & below brick work. |
| 16 | 15 mm cement plaster in single coat on fair side of single or half brick wall for exterior plastering up to floor two level including internal rounded angles chamfers, and/or roundedangles not exceeding 80mm in girth and finished even and smooth no extra for mixing any additive. (1)1 cement : 6 coarse sand. F.M. 2.25 |
| 17 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete. |
| 18 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade : New work (Two or more coats applied @ 1.43 ltr/ 10 sqm ove and including priming coat of exterior primer applied @ 2.20kg/ 10 sqm) |
| 19 | M.S. or Iron work in heavy sizes such as trusses, built up gates, record rack, roof work , gates etc wrought to required from including supply of steel bolts, nuts wastage etc and fixing required for proper completion of the work. |
| 20 | Painting two coat over priming coat (but including cost of priming coat) on steel and other metal surfaces up to 10 cm. width or girth or small articles not exceeding 0.10sqm in area white superior synthetic enamel such as LUXOL3,Hi-gloss apcolite superlac, DULUX specified brushing to give an even shade and including cleaning the surface of all dirt,dust and other foreign matter sand papering and stoping including cost of all materials, labour tools and plants etc. required for proper completion of the work. |
| 21 | Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used. With G.I. barbed wire |
| 22 | Centering & shuttering including strutting, propping etc. and removal of form for all heights: Foundations, footings, bases of columns, etc. for mass concrete |
| 23 | Lintels, beams, plinth beams, girders, bressumers and cantilevers. |
| 24 | Columns, Pillars, Piers, Abutments, Posts and Struts |
| 25 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). |
| 26 | G.S.T Extra as per applicable |