| 1 | Earth work in excavation of foundation trenches or drain in all sorts of soils (including mixed soil but excluding laterite or sand stone) including removing spreading ro stacking the spoils within a lead of 75 m, as directed including trimming the side of trenches, levelling dressing an raming the bottom, bailing out water etc. as required complete. (a) Depth of excavation not exceeding 1,500 mm. |
| 2 | Earth Work in filling of foundation trenches of plinth with good earth in layers not exceeding 15cmm including watering ramming etc.layer by layer complete ( payment to be made on the basis of measurement of finished quantity work) (a)With earth obtained from excavation of foundation. |
| 3 | (II) Cement concrete with 30 mm down graded shingles excluding shuttering. N.B. Variety a) 1:3:6 proportion. |
| 4 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.(b) River bazree. |
| 5 | Hire and labour charge for shuttering with centering and necessary staging upto 4m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slab, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto the roof of ground floor) . |
| 6 | Supplying & laying as per IRC-SP:063-2004 paver unit of any shade of approved quality as per relevant IS code, laid in pattern as directed in pavement, footpath, driveway (paver block only), etc including necessary underlay complete in all respect with all labour and material. [Border concrete if necessary to be paid separately]. Note: Sub-grade CBR should not be less than 5.(b) 50 mm thick interlocking designer concrete paver block M- 30 grade for non-traffic zone,buiding premises,garden,parks,domestic drive as per IS: 15658- 2006(over 20-30 mm medium sand bed on 200mm thk bound gnaular /granular base course including cost of sand for sand bed but excluding cost of base course & subgrade preparation.)(ii) Coloured Decorative |
| 7 | Plaster (to wall, floor, ceiling etc) with sand - cement-morter including rounding off and chamfering corners as directed and racking outjoints including throating, noising and drip course, scaffolding / staging where necessary ( Ground floor) (excluding cost of chipping over concrete surface )ii) With (1:4) Cement morter c) 10 mm thick plaster |
| 8 | Neat cement plunning about 1.5mm thick in wall dado, window sills, floors, drains etc. using cement @ .152 cu m/100 sq m |
| 9 | Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the EIC. In Ground Floor: (b) Two Coats. |
| 10 | Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer\"s specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer. In Ground floor (Two Coat) c) Super Protective 100% Acrylic Emulsion. |
| 11 | Earth work in filling in compound, tank, low land, ditches etc. with good earth, in layers not exceeding 150 mm. including breaking clods and consolidating the same by ramming and dressing complete. (Payment will be made on profile measurement before and after the work) (ii) With carried earth arranged by the contractor within a radius exceeding 3 km. but not exceeding 5 km. includingthe cost of carried earth. |
| 12 | Add GST @ 18% |
| 13 | Add Labour Wlfare Cess @1% |