| 1 | Detail of Work |
| 2 | Safe cartage of ST/ PCC poles up to 8.5/9/11/13 Mtr. from ESC, SRE/JE store to site of work at various sites including loading & unloading at both ends.(Dist.Up to 30 Km.) |
| 3 | Safely cartage of other complete line material / 11 KV XLPE cable / ABC cable(Except PCC /ST Poles) from ESC, SRE/ JE store to site of work at various sitesincluding loading, unloading at both ends.( Dist.App. 0 to 30 Km.) |
| 4 | Safe cartage of 63/ 100 KVA T/F from ESC,SRE, to the site of work including loading & unloading at both ends. (Dist. Upto 30 km.) |
| 5 | Safe cartage of 250 KVA T/F from ESC,SRE, to the site of work including loading & unloading at both ends. (Dist. Upto 30 km.) |
| 6 | Safe cartage of Fuse Set from ESC,SRE, to the site of work including loading & unloading at both ends. (Dist. Upto 40 km.) |
| 7 | Providing of PG Clamp |
| 8 | Erection of single support on ST/ PCC poles up to 8.5/9/11/13 Mtr Long with complete fitting of all accessories of11 KV/LT line. complete. |
| 9 | Erection of double Pole on ST/ PCC poles up to 8.5/9/11/13 Mtr Longwith complete fitting with all accessories complete. |
| 10 | Fixing of 11 KV stay rods by digging of pits in block of 600X600X300 mm. &withnozzling of stay wire 7/10 SWG and fitting the same on the pole |
| 11 | Concreting of stay rod inratio 1:4:8 with Ist class brick ballast with cement, sand |
| 12 | Providing and Fixing ofNumber Plate. |
| 13 | Earthing of poles by earthing rod |
| 14 | Providing ofAll type MS Clamp for ST/ PCC poles with nuts bolts made of new MS flat iron 50x6 mm. |
| 15 | Providing of J-Hook |
| 16 | Providingand fixing ofnuts & bolts of various sizes. |
| 17 | Providing and fixing ofSuspention clamp with I- Hook |
| 18 | Providingand fixing ofDead end clamp with I- Hook |
| 19 | Providing and fixing of Piercing connector Diff. size. |
| 20 | Fixing of 3 phase Distribution Box |
| 21 | Laying of LT Cable 1x25 sq.mm. from T/F to double pole. |
| 22 | Laying, lifting, Stringing, sagging jumpring & binding ofACSR Weasel Conductor for 11KV/LT Lineincluding complete. |
| 23 | Safe installation of 63/100 KVA T/F on the double pole with complete fittings including making connections and commissioning. |
| 24 | Construction of plinth for installation of 250KVA T/Fof size 1.5x1.5x1.5 Mtr. made of 9\" thick wall in all the four sides with 6\" thick RCC top duly filled with sand & plastered 12 mm. thick in ratio 1:4 with cement & sand on outer surface of brick wall . |
| 25 | Safe installation of 250KVA T/F on the Plinth with complete fittings including making HT connections and commissioning. |
| 26 | Laying and making connections of LT XLPE cable 3.5x240/3.5/150sq.mm. from T/F to double pole |
| 27 | Providing and fixing of wire mesh fencing size 2.5x2.5x2.5 mt. grouting making frame of MS angal 35x35x5 mm and fixing four no. MS strip size 25x6 mmat equal distance in between the frame and fixing square mesh 50 mm square in each frame the fencing should cover all side of T/F with providing 1 No. door size 6’x3’ with sitakni & Dandala. |
| 28 | Safe installation ofFuse with complete fittings including making connections and commissioning. |
| 29 | Laying, lifting, Stringing, proper sagging ABC cable of size 3x50+1x35+1x16/ 3x95+1x70+1x16/ sq.mm. including fixing ofall accessories. |
| 30 | Providing and fixing of Danger Board with clamp |
| 31 | Concreting of PCC/ST poles SP-55, 8.5/11 Mtr.long with cement concreting in bolck of 600X600X1500 MM. in ratio 1:4:8 with cement, sand and brick ballast size 1\"\"x1.5\"\" with plinth. |
| 32 | Chemical Earthing of 250 KVAT/F |
| 33 | Off shooting of tree branches touching the 11 KV/LT line. |