Tender For Work Of Developing Upvan With In Municipal Corporation Limits. - Boundary wall and path construction work.2 Excavationinfoundation in ordinary soil (loam,clay orsand)including,liftupto1.50mandleadupto 30mandincludingfillingwateringandramming .....................................including all complete.3 Providingandlaying cementconcrete in 1:5:10 stoneballast approved coarse sand and cement. Curingcompleteincludingofcostofformworkin foundationand floors.4 Providing and laying in position 1:1.5;3 cement concrete in Raft foundation, including the cost of centering, shuttering, finishing and excluding reinforcement - All work up to plinth level in (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). (Sl No. 5.15 Reinforced cement concrete work in1:1.5:3 in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc. including cost of centering, shuttering, finishing and excluding reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). PWD- 5.2 up to plinth level6 Same as item no. 04 above plinth level7 Reinforced cement concrete work in beams,lintel suspended floors, roofs having balconies, shelves, chajjas, bands, staircases and spiral stair cases above plinth level up to floor five level, including the cost ofentering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stoneaggregate 20 mm nominal size)PWD- 5.38 M.S or Iron work in plain work such as reinforced concrete or reinforced brick work (When not included in and an over all rates) brought to required shape as necessary of the work and including the supply of steel and its wastage bend, hooks and authorized over lapping shall be measured upto floor to level.( As per Analysis of rate)9 M-150 B/W in 1:4 Cement and coarse sand mortar mortar in Foundation including supply of all materials, labor and tools and plants, etc. required for proper completion of the work. (S.I. No.10 M-150 B/W in 1:4 Cement and coarse sand mortar mortar in super structure including supply of all materials, labor and tools and plants, etc. required for proper completion of the work.11 12 mm thick cement plaster in single coat on fair side of single or hair brick well for interior plastering upto floor two level including brick wall for plastering upto floor two level including internal rounded angles not exceeding 80 mm in girth,hamfers and finished even and Stooth. No. extra for mixing any 1 cement : 4 coarse sand(S.I. No. 17.5812 Providing and fixing 18 mm thick Granite (gang saw cut) mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations, of required size, approved shade, color and texture laid over 20 mm thick base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing, molding and polishing to edges to give high gloss finish etc. complete at all levels. (Slab area above 0.50 Sq.M.)13 Providing and laying 80 mm thick i-Shaped & zig-zag shaped gray interlocking tiles over 30 mm thick local sand base leveling and dressing of surface required level and slope, filling joints with local sand all complete.(As per Analysis)14 Providing and laying 80 mm thick i-Shaped & zig-zag shaped colored interlocking tiles over 30 mm thick local sand base levelling and dressing of surface required level and slope, filling joints with local sand all complete.(As per Analysis)15 Proving and laying cement concrete in 1:2:4 with cement, coarse sand and 20mm guage stone aggregate, curing complete, including cost of form work. (Sl No. 279)16 Mild steel or iron work of small size and sections such as holding down bolts, hold fast, tie rods, grating etc, (when not included in an overall rates) wrought to required shape as necessary for bending etc including supply of steel and its wastage including cost of bolts, nuts if required, welding, grinding and making holes as required for completion of work. (Sl No. 502)Gate and grill17 Applying primer and Painting on iron works in small areas or new wood work with one coat of ready mixed priming paint & one coat of approved superior ready mixed paint of clear synthetic varnish including supply of all materials, labor and T & P etc. required for proper completion of work. (Sl No. 641+19.29+642)18 Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete. DSR-13.2619 Finishing walls with exterior emulsion paint (Apex) of approved brand and manufacture and of required shade on undacorated wall surface to give even shade over @ 1.25 Ltr/10sq m including one coat of primer applied @ 0.75Ltr/10sq m coat curing and cost of all material, labour, T&P etc. required for proper completion of work.for two coat. Sl nO.- 66020 Providing and fixing glass mosaic tiles on finished wall............Complete. (DSR 11.53 - factor)21 Supply and Fixing Fountain with Lights................................ including all complete.22 Supply and fixing RCC Garden Benches .......................... including all complete.23 Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c ......... including all complete.24 Supply and fixing of 12.00mtr Highmast light in the park…………..including all complete.25 Supply and fixing Manak board…………………….. All Complete.26 Construction of Silla patt board using brick work and granite stone…………………….. All Complete.Tree plantation work from 27 Miyawaki.28 Demarcation and gradation29 Expenses on making on land scale30 Soil testing31 Soil analysis and soil enrichment nutrient material32 Manure (6000kg/1065cum)33 Straw34 Coco pit35 Drum of 200 liter capacity36 Bucket37 Hazara38 Chopped grass39 Straw40 Material for preparing Jeevamrut41 Desi/Pahari cow urine42 Cow dung43 Pulses flour-gram flour44 Jaggery45 Supporting stick for supporting the plant, 5 feet long, strong and solid shape (25 mm diameter and 2.5 m long bamboo twenty nos. 400.00) Dar 2020 Hort-205) Based46 Jute thread47 JCB Construction of 1 meter deep and 1 meter wide trench on the ground using machine (Excavator).48 Spreading half of the biomass mixture evenly in the trench and the other half on the soil mound.49 JCB Mixing of biomass by machine50 Digging a small pit on the mound with a phauda in which the plants can sit comfortably51 Plantation of Trees, Shrubs and Hedge at site i/c watering and removal of unsavericable materials as per direction of officer in charge (excluding cast of plant & water) (DAR 2020 Hort-2.57-1) based52 Cost of plants 3% extra53 Ficus black yellow54 Neem55 Sesame56 Kadam57 Ashok58 Silver Oak59 Alstonia60 Oleander61 Chandni62 Calandra63 Croton64 Mehndi65 Kachnar66 Hibiscus67 Half Chandni68 Lal Badshah69 Analmi70 Haveli71 Raat Rani72 Bougainvillea73 Tikoma Desi74 Bottle Palm75 Ficus76 Alba Champa77 Golden Bottle Brush78 Maintinance of plants upto One Year including irrigation by air gun, Hoeing, weeding and repairing of stack etc. all complete of the work as per I/C & guide line of miyawaki method. (1x4328x0.48=2077.00)79 Mulching process two time in a year of total planting area….............(foest deptt rate) (1x2x15472=30940.00)80 Submersible Pump81 Submersible pump set iSt marked including cable starter etc. 03 HP Single Phase 120 Meter head Pluga Make82 125 mm dia PVC pipe (10 KG/cm2)83 32 mm dia G.I Pipe (Medium Class)84 Bleaching powder.85 125mm dia PVC end Cap86 Plastic net to cover the slots of PVC pipe87 Solution of jointing PVC pipe.88 4 mm2 Copper Cable for submersible pump.89 Transportation of material. T&P etc. to the site of work loading unloading & proper stacking at the site, including return cartage of unused material equipment and T&P etc to departmental store complete.90 Digging the pit for boring work including dismantling of C.C., earth filling and reinstatement of CC, supply af all labour, T&P with arrangement of water required including of all material labor T&P etc. all comelets,91 Construction of 200 mm dia bore hole by local Rig machine in ordinary soil with kankar, bajri etc. including transportation of material, lacal cutter machine, errection of machine and its dismantling after completion of work including hiring charge of all T&P including of all material labor T&P etc required for completion of work.0-145 M BGL.92 Lowering of pipe assembly in 200 mm bore hole including all labor T&P required for jointing the various components and lowering them in to the bore hole upto proper depth etc. complete.0-140M BGL.93 Supply of Pee Gravel shrouding and packing between the bore hole wall & PVC lowering 125mm dia 10 kg/cm294 Installatin of 03 HP submersible pump motor Aure wish 32mm G.t. lowering (submersible Cable drem, & installation of starter) Including any ef labour, TAP etc. complete.95 Development of bore till the discharge Is free on turbidity by compression including labor aird for completion work.96 construction of brick work 1:6 chamber of size 80cm 100cm x 1.0m ( inside) Including Its SCC cover 1:214 of size 1.10mx 1.10m of thickness 10cm for safety of boring & submersible motor pump set including supply of all material labor T&P etc. complete.97 water supply pipe line98 1 PVC Pipe99 1 Ball Valve PVC100 1 Elbow G.I101 1 Socket G.I102 1 Union G.I103 1 Nipple 6 Long G.I104 1 Tee G.I105 Hook106 Selic107 Labour Charge(digging, making 1’’ connection and pipe fitting work.)108 Approach road109 Excavation in foundation in ordinary soil (loam, clay or sand) including, lift up to 1.50 mandle up to 30 mand including filling watering and ramming ….. ………………… including all complete.110 Construction of granular sub-base by providing well graded material, spreading in uniform layers wth motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheelo roller to achieve the desired density. complete as per technical specification clause-401 (As per Analysis of Rate)111 Providingandlaying cementconcrete in 1:5:10 stoneballast approved coarse sand and cement. Curingcompleteincludingofcostofformworkin foundationand floors.112 Providing and laying in position 1:1.5;3 cement concrete in Raft foundation, including the cost of centering, shuttering, finishing and excluding reinforcement - All work up to plinth level in (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). (Sl No. 5.1)113 Reinforced cement concrete work in1:1.5:3 in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc. including cost of centering, shuttering, finishing and excluding reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). PWD- 5.2 up to plinth level114 CEMENT CONCRETE PAVEMENT(C.C ROAD) Construction of unreinforced cement concrete road with cement, coarse sand and stone grit and fixing of 125 micron thick polythene film, ..... …………….Complete Chapter- 20 (New Item)115 R.C.C work in slab with cement, coarse sand and 2 cm (3/4) gauge approved stone grit in the promotion 1:2:4 excluding supply of reinforcement and its bending and including its fixing and binding the same with 24 BWGI binding wire and including necessary centering and shuttering etc and also including supply of all materials labor and tools and plants etc. required to proper completion of the work/strength of the concrete shall not be less than M-15.(DSR/PWD 284)116 M.S or Iron work in plain work such as reinforced concrete or reinforced brick work (When not included in and an over all rates) brought to required shape as necessary of the work and including the supply of steel and its wastage bend, hooks and authorized over lapping shall be measured upto floor to level.( As per Analysis of rate)117 LED lights118 Supply and fixing of 7 mt. G.I. Octagonal Pole of approved make (top dia 70mm, bottom dia 130mm and base plate 12mm thick) having 3mm thickness with single arm bracket (1 Mtr. length) on R.C.C. foundation drilling including the cost of foundation, foundation bolts, excavation & back filling and required T & P complete in all respect.119 Supply and burying of safe earthing electrode T-19 (Hot Dip Galvanized) length upto 2000 mm, outer G.I. Pipe 50 mm, Inner Pipe 25, terminal dia 12mm, outer G.I. pipe of 16SWG and inner G.I. pipe of 12 SWG with Hot Dip Galvanized up to 100 micron filled with crystalline conductive mixture (CCM) having anti corrosive and conductive property with 50 Kgs activated soil (BFC) capable of reducing the soil resistivity with good mixture of retaining capacity along with 30cm square C.I. frame with hinged over & masonry housing from electrode terminal to switch board costof 25 x 3 G.I. strip will be extra.120 Supply and laying of aluminum conducter, PVC insulated armoured, served, sheeted cable 1000 bolts grade at a depth of 750mm below ground level over a cushion of 75mm thick sand alround and protected with burnt bricks on sides and top on surface, the cable run shall be fixed on M.S. clamps etc. of suitable size. (16 sqmm4 core)121 Supply and fixing of LED street light fitting having dia cast aluminum body and diffuser with driver set suitable for 72-90 watt confirming to IP 65-67 protection complete in all respects.122 S/F of Mica Junction Plate with MCB and connection pin123 S/Laying of 63/90 mm P.V.C. Pipe etc.complete in all respect. Including clamp124 Supply & fixing of plain type aluminum lug to the cable leads included with tape and making connection etc.125 Supply & laying of 1.5 mm x 2 core copper cable Under pole.126 Numbering Pole with Base of white base.127 IInd Year Maintenance128 Mantinance of plants upto One Year including irrigation by air gun, Hoeing, weeding and repairing of stack etc. all complete of the work as per I/C & guide line of miyawaki method129 Mulching process two times in a year of total planting area......(foest deptt rate)130 Third Year Maintenance131 Mantinance of plants upto One Year including irrigation by air gun, Hoeing, weeding and repairing of stack etc. all complete of the work as per I/C & guide line of miyawaki method132 Mulching process two times in a year of total planting area......(foest deptt rate)