| 1 | Erection of 22kV H.T Line |
| 2 | Erection of 10mtr. Long ST pole. |
| 3 | Erection of pole.Digging of pit,(ii) Laying of RCC muff (iii) Drilling of holes in X-bracing set, X-arms (iv) Erection of pole (v) fixing of insulator,X-arm, Knee bracing set, Top Clamp (vi) fixing of Barbed wire, Danger plate (vii) filling of pit & Ramming i/c painting of pole S/Pole str. (Complete in all respect). |
| 4 | Re erection/erection of stay set (HT). |
| 5 | Digging of pit, fixing of stay rod, filling of pit, Nozzeling & Tighting.) Complete in all respect. |
| 6 | SAGGING OF ACSR CONDUCTOR 6/1/3.35mm (Single wire). |
| 7 | stringing & sagging, Binding with insulator (only). |
| 8 | Sagging of G.I Wire for earth wire |
| 9 | Erection of 25KVA S/Stn. |
| 10 | Digging of pit for pole and earthing, drilling of holes in x-arm, preparation of plate form, Str. MemberC.I A.I. X-arm, knee bracing set, erection of D-pole, c.c.muff, erection of plate form, erection of x-arm, dropout fuse unit, lightning arrester, MCCB switch, L.T box, energy meter, erection of transformer, G.O switch, stay set, jumper earthing 3 sets, L.T cables, paintingetc. (Complete in all respect). |
| 11 | Providing Fencing around the Sub-station. |
| 12 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50 m. All kinds of soil |
| 13 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering-All work up to plinth level: 1:4:3 (1 Cement: 4 coarse sand): 5 graded stone aggregate 40 num nominal size) |
| 14 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level 11.5.3 (1 cement: 1.5 coarse sand) 3 graded stone aggregate 20 mm nominal size) |
| 15 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 16 | Providing and fixing G1 chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge. Made of GI wire of dia 4 mm |
| 17 | Providing and fixing ISI marked M.S. pressed butt hinges bright finished with necessary screws etc. complete 100x35x1.90 mm |
| 18 | Providing and fixing 151 marked oxidised M5. sliding door bolts with nuts and screws etc. complete 250-16 mm |
| 19 | Loading /unloading charges of transformer & other s/stn. Material. |
| 20 | ERRECTION OF L.T LINE ON 9Mtr. Long S.T pole. |
| 21 | (i) Digging of pit, Laying of RCC muff,Drilling of holes in poles.Erection of pole,Erection of shackle insulator, filing of pit and ramming, Painting of pole. (Complete in all respect). |
| 22 | ERRECTION OF STAY SET |
| 23 | Digging of pit, fixing of stay rod, filling of pit, Nozzeling & Tighting.) Complete in all respect. |
| 24 | SAGGING OF ACSR CONDUCTOR 6/1/2.59mm (Single wire). |
| 25 | Laying of conductor, stringing & sagging, Binding with insulator (only). |
| 26 | Sagging of G.I Wire for earth wire |
| 27 | MATERIAL TO BE SUPPLIED BY CONTRACTOR (Subject to the non-availability of material at Divisional Store). |
| 28 | Prov. RCC Muffs 2Mtr. |
| 29 | Prov .Shakle Insulator (16KN) |
| 30 | Prov .D-Iron (U-Clamps) |
| 31 | Prov. Nuts & bolts. |
| 32 | Prov. Aluminium paint. |
| 33 | Prov. Stay clamp |
| 34 | Prov. Egg Insulator. (LT) |
| 35 | Prov. Egg Insulator. (HT) |
| 36 | Prov. LT stay Wire (7/3.15mm) |
| 37 | Prov. Disc Insulator Set (including Dead end clamp,Ballcleaves eye sockets, straight stapple & Bend Stapple etc.) |
| 38 | Prov. 22kV Pin Insulators with GI Pin. |