| 1 | 63KVA, 11/0.4KV SUB-STATION Muffs (2000 mm) with concerete filling |
| 2 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for incommer line |
| 3 | MS Angle Iron (50X50x6 mm), Length: (2800 mm) x1 Nos for LA\"s |
| 4 | X-Arm: [Channel Iron (75x40x6 mm), Length : (2800mm) X 4 Nos] for supporting DO fuse unit & GO switch |
| 5 | Transformer Bed, Belting & Knee Bracing X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed |
| 6 | X-Arm [Channel Iron (100x50x6 mm), Length : 460mm x 2 Nos for supporting Main Channel of Transformer] |
| 7 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 8 | MS Angle Iron (35X35x5 mm), Length : (460 ) x 2 Nos |
| 9 | MS Angle Iron (50X50x6 mm), Length : (950 mm) x 2 Nos for Bed Knee Bracing |
| 10 | Transformer LT Distribution Box and GO Switch fixing Assembly MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 11 | MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 12 | GO Switch Handle Supporting: [Channel Iron (75x40x5 mm), Length : 460 mm |
| 13 | Prov. GO switch |
| 14 | D.O Fuse Unit |
| 15 | Surge Arrester, 9 kV Station Class(Porcelain Type) |
| 16 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 17 | Stay set complete |
| 18 | Stay Wire (7/3.15 mm) (7.0 kg Per Stay Set) |
| 19 | Prov. Pipe Earthing Set |
| 20 | 6 SWG GI wire For Earthing |
| 21 | LTDistribution panel box with MCCB. For 63 KVA |
| 22 | Prov. Half Clamp (M.S. Flat 50X6 mm) |
| 23 | Prov. Full Clamps (M.S. Flat 50X6 mm) |
| 24 | Prov. Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more(with flat and spring washers)] |
| 25 | Prov. Aluminium Thimble |
| 26 | Prov. Copper Thimble 200 Amp |
| 27 | Prov. Danger Plate |
| 28 | Prov. Barbed Wire |
| 29 | Prov. LT Cable 3.5 X 120 mm² |
| 30 | Prov.LT Energy Meter (3-ɸ, 4 wire CToperated Static Tri-Vector meter ) (CT-200/5 A)for 63 KVA T/F |
| 31 | a) Prov. Aluminium Paint. |
| 32 | b) Prov. Red oxide |
| 33 | LT Switched Capacitors 9- KVAr for 63 KVA (rate per 27KVAr) |
| 34 | Chain Link fencing , Angle Iron ,Gate etc for transformer fencing |
| 35 | LT Line Prov. RCC Muff with concrete filling |
| 36 | Prov.Single Continous Earth wire (GI, 8 SWG) {alongwith 2 wire lengths for avg. one road crossing @ 20 m and Additional 1% (Sag and wastage)} @ 0.102 kg/m kg |
| 37 | Prov. LT stay set |
| 38 | Prov. AAAC 7/2.50 mm |
| 39 | Prov. Stay wire 7/3.15mm (@6.0 Kg per stay set) |
| 40 | Prov. X-Arm (Horizontal) MS Channel Iron: 100X50x6, Length [950 mm] |
| 41 | Prov. Full/Stay Clamp |
| 42 | Prov. Half Clamp |
| 43 | Prov.Egg insulator |
| 44 | Prov. LT Shackle insulator |
| 45 | Prov. D-iron |
| 46 | Prov. Nuts & Bolts Off Size |
| 47 | Pro. Aluminium paint |
| 48 | Erection of S/Stn.Structure using Steel Tubular Poles a/w RCC Muff & its concrete filling as per latest standard practices /specification of REC / HPSEBL including digging of pits, erection of Poles & Muffs, Filling muffs with PCC mixture, re-filling of pit & ramming, drilling of holes in Cross X Arms, Preparation of Plateform Structure Members MS Channel X Arms and Knee Bracing Sets, Erection of Plateform, fixing of M.S. Cross Arms S/Stn fitting, Painting of Complete structure with red oxide paint & then alluminium paint, fixing ofGO Switch, DO fuse units, Lightening Arrestors, Disc Insulators, Pin Insulators, LT Ditribution Panel, Energy Meter. Erection of S/Stn. Pipe Earthing Set (3Nos.) complete in all respect including providing Char Coal, Salt etc.,Erection of Transformer, Providing Earthing Connection to GO Switch, Transformer Lighteneing Arrestor etc. Erection of Stay Sets, Erection of LT Cable and fixing of jumpers. Testing and commissioning of Transformer and allied equipments complete in all respect. |
| 49 | Erection of LT Line Pole structure with Steel Tubular Pole 9 mtr. Long as per latest standard practices /specification of REC / HPSEBL : (including Digging of pit for pole, muffing of pole, erection of poles, refilling of pit & ramming , drilling of holes in pole and X-arm, fixing of X-arm, Shackle Insulators and painting of structure with Redoxide Primer & Aluminium Paintetc.Complete in all respect as per the standard practices / specifications of the REC /HPSEBL. |
| 50 | Erection of Stay Set (LT) as per latest standard practices /specification of REC / HPSEBLincluding digging of pit (size0.9*1.20*1.33),fixing of Stay Rod, filling and ramming of pit, nozzelling and tightening etc. complete in all respect. |
| 51 | Laying of Conductor, Stringing, Sagging ofAAAC, 30 mm²and binding with Insulators (3 wires) and fixing of jumper. |
| 52 | Laying ofEarth wire with GI Wire 8SWG , Stringing, Sagging ofand binding with Insulators. |
| 53 | Add Loading unloding of 3 no. pole, 01 no T/F at site & store for complete job. |
| 54 | Add Testing & Commissioning Charges DTR LT |
| 55 | Labour cess @1% on (Material Cost +Erection + Transportation+ GST + Testing & Commisioning Charges) etc. |