| 1 | Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed. (a) By manual means :(ii) From 50 mm to 100 mm thick. |
| 2 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. |
| 3 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches |
| 4 | Providing and laying Design Mix concrete for plain / reinforced concrete work in any part of bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding cost of labour and materials for formwork & reinforcement works. (a) M-15 GradeUsing concrete mixer. |
| 5 | Hire andlabour charge for shuttering with or without staging up to 4.0m height using approved stout props without wooden planks /ply Wood/ steel sheet plate with required bracing for any kind of plain Or reinforced concrete works in all sorts of minor structure including Culvert, box culvert, cross-drain etc. The rate is inclusive of fitting Fixing and striking out after completion of work as per specification And direction. a)where staging is required b)where staging is not required. (a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-In-Charge. |
| 6 | Construction of Sub Base using Local Materials, spreading in uniform layers with Motor grader on prepared surface, including screening the metal as necessary, mixing by mix in place method withRotavator at OMC, and compacting with vibratory roller to achieve the desired density, lighting, guarding and barricading including cost and carriage of all materials and making necessary earthen bundh of one metre wide on each side to protect the edges complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(iv) For Construction of Sub Base by compacting Add cost at site of 1.28 m³ of materials to arrive at the complete rate. river bed materials. |
| 7 | (b) 50 mm thick interlocking designer concrete paver block M 30 grade for non-traffic zone,buidingemises,garden,parks,domestic drive as per IS: 15658- 2006(over 20-30 mm medium sand bed on 200mm thk bound gnaular /granular base course including cost of sand for sand bed but excluding cost of base course & subgrade preparation.) ii) Coloured Decorative |
| 8 | Providing & fixing Concrete Sign Board as per IRC specification of size 900 x 750 x 37 mm. thick made with RCC 1:1½:3 with pakur variety stone chips reinforced with double layer IRC febric (75 x 75 mm. mesh) and fixed with necessary nuts & bolts on two RC precast posts 100 mm. x 150 mm. of height 2.65 mm. of which top 750 mm. is of section 100 x 13 mm. and 1.90 metre above GL & 0.75 metre below GL including digging hole, repacking the same with cement concrete 1:3:6 with jhama khoa or with local stone chips etc. complete including painting two coats on both faces lettering sign marks etc. as per direction of the Engineer-in-Charge. (The rate is inclusive of cost of reinforcement, concrete, shuttering, nuts & bolts, washer etc. complete.) |
| 9 | GST |
| 10 | Labour Cess |