| 1 | CENTRALIZED MATERIALS,Loading unloading & safe cartageand errection of new STP/PCC Poles and othermaterials from Electricity store center, Robertsganj to the work place and proper stocking. (Distance up to 80Km.) |
| 2 | STP Pole 11 mtrs long |
| 3 | PCC Pole 8.5 Mtrs Long |
| 4 | 11KV Disc Insulator with fitting |
| 5 | 11KV Pin Insulator with Pin |
| 6 | ACSR Weseal Conductor |
| 7 | ABC (3x95+1x70+1x16)sqmm |
| 8 | ABC (3x120+1x70+1x16)sqmm |
| 9 | LT AB Cable (1*16+1*25) |
| 10 | 25 KVA T/F 11/0.4KV NEW |
| 11 | 10 KVA T/F 11/0.4KV NEW |
| 12 | DE-CENTRALIZED MATERIALS, Provided Contractor |
| 13 | X-Arm holding clamp with nut & bolt |
| 14 | Danger Board with nut & bolt |
| 15 | X-Arm M.S. Angle(65*65*6)mm V-Type 11KV |
| 16 | M.S.Channel (125*65*1300)mm T-Off |
| 17 | M.S. Chaneel Dropper(100*50*6)mm Long |
| 18 | Stay Complet ( Stay rod 16*1800mm, Stay wire 5 kg, Stay clamp, bolt & nut with grouting) |
| 19 | Earthing Complete |
| 20 | Top Channel (100*50*2240) |
| 21 | Cross Brasing Angle |
| 22 | G.I. Wire 6SWG |
| 23 | LT Shackle Insulator |
| 24 | Clamp for top /Dropper/T-OFF Channel with Nut & Bolt |
| 25 | F-Bracket with nut &bolt |
| 26 | Dead end clamp lt with i hook |
| 27 | Piercing cable connector of size 120 & 95 |
| 28 | Suspension Clamp |
| 29 | Eye Hook with clamp |
| 30 | LT Distribution Box |
| 31 | Clamp for distribution box |
| 32 | Barbed wire |
| 33 | PG Clamp for Weasel conductor |
| 34 | Clamp for LT with nut bolt etc |
| 35 | S/S Base for T/F |
| 36 | Nut &bolts for shackel |
| 37 | LT shackel strip with nut &bolts for LT section pole |
| 38 | stay clamp with nut bolt |
| 39 | Various type nut &bolts |
| 40 | SERVICE CABLE(ARMORED CABLE) 6MM |
| 41 | TF Holding Clamp |
| 42 | Stone Pad(300*300*75)mm |
| 43 | Work of following materials as Per RESSPO/PuVVNL norms at the work site. |
| 44 | Erection of Sectional Four Pole Structure , Sectional Double Pole Structure and single support ST/PCC pole for construction of 11 KV line including digging of pit, fitting of all accessories, back filling of earth & others required work. |
| 45 | Grouting of pole with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) |
| 46 | Stringing of ACSR Weseal Conductor along with fitting of all accessories |
| 47 | Stringing of LT ABC 3*120+1*95+1*16 Sqmm along with fitting of all accessories |
| 48 | Stringing of LT ABC 3*95+1*70+1*16 Sqmm along with fitting of all accessories |
| 49 | Stringing of LT ABC (1*16+1*25) Sqmm along with fitting of all accessories |
| 50 | Installation of LT Distribution Box |
| 51 | INSTALATION OF 10 KVA T/F with all accessories |
| 52 | INSTALATION OF 25 KVA T/F with all accessories |
| 53 | Hard Rock Cutting (Digging ) for Pit of Pole due to Hill area |
| 54 | Hard Rock Cutting (Digging ) for Pit of stay due to Hill area |
| 55 | Grouting of stay with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) |