| 1 | Demolishing R.C.C. workmanually /bymechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 2 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil. |
| 4 | Supplying and filling in plinth withsand under floors, including watering, ramming, consolidating and dressing complete. |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement:3 coarse sand (zone-lll) de.ived from natural sources:6 graded stone aggregate 40 mm nominal si2e derived from natural sources) |
| 6 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars |
| 8 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form work for :Foundations, footings, bases for columns |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form for:Foundations, footings, bases of columns, etc. for mass concrete |
| 11 | Collecting & Transporting the old Rails (52 kg) from nearby rail track yards to the working site & stacking at a suitableplace as per direction of the EIC. Incl. all lead & lift etc.complete. |
| 12 | Cutting the Rails of required length & making necessary holes as per requirement & erecting the same in vertically at a required distance in the existing earthpit & grouting the same with C.C 1:1.5:3 etc.complete as per the direction of the Engineer-in-charge (C.C 1:1.5:3 will be paid separately) |
| 13 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 14 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two or more coats on new work |
| 15 | Total impact of GST plus Labour Cess [@ 1 % (BOCW Cess to be deducted from the RA bill as per the value of the work progress)] for the purpose of CTC |