| 1 | Earthwork in open / Surface Excavation not exceeding 300mm in depth but exceeding 1.5m in width as well as 10 sq.m on plan in all types of soil, mixture of gravel and disintegrated rock, hard stiff clay including grading and levelling neatly by breaking clods, disposal of excavated earth upto 50m lead & lift upto 1.5m, (Disposed soil to be levelled by breaking clods, if any and neatly dressed) etc., all complete as per specifications. |
| 2 | Providing and laying in position of plain cement concrete using hard granite broken stone for all insitu levelling courses in foundations, floor, roof screeding, encasing pipes, etc., including mechanical mixing, ramming, compaction, levelling, curing, dewatering, if any including the cost of formwork etc., all complete as per specifications. |
| 3 | 1 : 2 : 4 (1 cement : 2 sand : 4 graded stone aggregate 20mm nominal size) |
| 4 | 1 : 3 : 6 (1 cement : 3 sand : 6 graded stone aggregate 40mm nominal size) |
| 5 | Supplying and filling in basement and foundation with sand including conveyance by lorry load, filling in layers of not more than 150mm in depth, each layer shall be well consolidated including watering, and dressing, levelling and dressing the top surface, etc., all complete as per standard specifications and as directed by Engineer- in-Charge. |
| 6 | Providing and fixing the following children\"s play equipments of make \"Arihant\" (or) \"Ankidyne\"made up of GI pipe, FRP, sheets, Galvanised sheet metal components, PU coating exposed metal surface, etc., as per manufactured drawing including transporting, errecting the play equipments over RCC pedestal, etc., all complete as per manufacturing specification and as directed by the Engineer-In-Charge.Note:- Cost of Earth work & Concrete works for erection of equipments will be paid for separately under relevant items. |
| 7 | See saw 2 seater FRP |
| 8 | See saw 4 seater FRP |
| 9 | Spring rider Duck |
| 10 | Spring rider horse |
| 11 | Merry Go round 4 seater (FRP seat) |
| 12 | Slide Junior FRP |
| 13 | Slide Senior FRP |
| 14 | Swing 2 seater (FRP seat with SS chain) |
| 15 | Loop Rung |
| 16 | Spiral slide Junior |
| 17 | Jungle gym |
| 18 | Circular climber |
| 19 | Providing and fixing the following Fitness equipments of make \"Arihant\" (or) \"Ankidyne\"made up of GI pipe, FRP, sheets, Galvanised sheet metal components, PU coating exposed metal surface, etc., as per manufactured drawing including transporting, errecting the play equipments over RCC pedestal, etc., all complete as per manufacturing specification and as directed by the Engineer-In-Charge.Note:- Cost of Earth work & Concrete works for erection of equipments will be paid for separately under relevant items. |
| 20 | Double bar/parallel bar |
| 21 | Leg Press Single Seater (Squat pushing) |
| 22 | Hip Twister Single person - Sitting/Standing any |
| 23 | Double Shoulder Wheel-Single person |
| 24 | Air walker Single person |
| 25 | Sky walker Single person |
| 26 | Double Sit up station |
| 27 | Single sholulder wheel-single person |
| 28 | Seated chest press single |
| 29 | Disposal of surplus excavated earth / Debris by collecting, loading, transporting by mechanical means and unloading them at places as shown by the Department within a lead specified below and levelling, etc., all complete as per specifications and as directedby the Engineer-in-Charge.Note: 1) The rates in respect of this item are applicable for the NET Quantities arrived at after making deductions for voids @ 20% in respect of soil and @ 50% in respect of rock from the corresponding stack / truck measurements.2) The earth shall be dumped well inside the dumping yard and not over approach pathway road. |
| 30 | Exceeding 1 Km but not exceeding 2 Kms |
| 31 | Dismantling Plain cement concrete/Brick bat coba at all lifts including clearing and depositing the same with a distance of 100 metres as directed by Engineer-in-charge. |
| 32 | Dismantling Brick workin cement mortar at all lifts including clearing and depositing the debris within a distance of 100 metres all as directed by Engineer-in-charge. |
| 33 | Dismantling RR Masonry in cement mortar at all lifts including stacking of RR stone, clearing and depositing the debris within a distance of 100 metres all as directed by Engineer-in-charge. |