| 1 | Deweeding and desilting work |
| 2 | Dewatering of pond 10 HP mud pump including all complete. |
| 3 | Dewatering of pond 5 HP mud pump including all complete. |
| 4 | Excavation and desilting work of pond including all complete. SI No.252 |
| 5 | Disposal of mud/malaba/deselting earth out side of munciple limit including all charges all complete. |
| 6 | R.C.C. Retaining Wall around of pond |
| 7 | Excavation in foundation in ordinary soil (loamelay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth up to a distance of 30m. from the foundation trenches including all T&P. Si no.-251 |
| 8 | Providing and laying in Cement concrete 1:4:8 (1Cement:4 find sand :8 graded stone grit 40mm nominal size) and curing complete, including cost of formwork in foundation. SI No.-281 |
| 9 | R.C.C. 1:1.5:3 with cement coarse sand and 20 mm stone grit in R.C.C. raft foundation and footing works all complete. Sl No. 287b |
| 10 | Mild steel or iron in plan work sheh as reinforced concrete or reinforced brick work(when not included in overall rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorized overlapping shall be measured up to floor two level.. SI No.- 504 |
| 11 | R.C.C. 1:1.5:3 with cement coarse sand and 20 mm stone grit in R.C.C. wall works all complete. SI No. 288b |
| 12 | Walking Area around of Pond |
| 13 | Earth work cutting/filling with 4.00 km cartage including all complete. |
| 14 | Providing and laying in Cement concrete 1:4:8 (1Cement:4 find sand:8 graded stone grit 40mm nominal size) and curing complete, including cost of formwork in foundation. SI No.-281 |
| 15 | R.C.C. 1:1.5:3 with cement coarse sand and 20 mm stone grit in R.C.C. Slab works all complete. SI No. 284b |
| 16 | Mild steel or iron in plan work shch as reinforced concrete or reinforced brick work(when not included in overall rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorized overlapping shall be measured up to floor two level.. SI No.- 504 |
| 17 | 75mm thick rubbed stone flooring over 20mm thick based of cement mortar 1:5 with join 3mm thick, side buttered with cement mortar 1:2 admixed with pigment to matched the shade of stone and pointing with same mortar. (Red Stone) |
| 18 | Construction of pond Bank (Ghat) |
| 19 | Excavation in foundation in ordinary soil (loamelay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth up to a distance of 30m. from the foundation trenches including all T&P. SI no.-251 |
| 20 | Providing and laying in Cement concrete 1:4:8 (1Cement:4 find sand a graded stone grit 40mm nominal size) and curing complete, including cost of formwork in foundation. SI No.-281 |
| 21 | R.C.C. 1:15:3 with cement coarse sand and 20 mm stone grit in R.C.C. raft foundation and footing works all complete. SI No. 287b |
| 22 | Mild steel or iron in plan work shch as reinforced concrete or reinforced brick work(when not included in overall rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorized overlapping shall be measured up to floor two level.. SI No.- 504 |
| 23 | M-150 brick work in 1:4 with cement coarse sand including all complete. SI No. 305b+309 |
| 24 | Struck pointing with cement mortar consisting one part cement and two part of sand including all complete. SI No. 578 |
| 25 | 75mm thick rubbed stone flooring over 20mm thick based of cement mortar 1:5 with join 3mm thick, side buttered with cement mortar 1:2 admixed with pigment to matched the shade of stone and pointing with same mortar. (Red Stone) |
| 26 | Construction of pond Bank (Ghat) |
| 27 | Excavation in foundation in ordinary soil (loamelay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth up to a distance of 30m. from the foundation trenches including all T&P. SI no.-251 |
| 28 | Providing and laying in Cement concrete 1:4:8 (1Cement:4 find sand a graded stone grit 40mm nominal size) and curing complete, including cost of formwork in foundation. SI No.-281 |
| 29 | R.C.C. 1:15:3 with cement coarse sand and 20 mm stone grit in R.C.C. raft foundation and footing works all complete. SI No. 287b |
| 30 | Mild steel or iron in plan work shch as reinforced concrete or reinforced brick work(when not included in overall rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorized overlapping shall be measured up to floor two level.. SI No.- 504 |
| 31 | M-150 brick work in 1:4 with cement coarse sand including all complete. SI No. 305b+309 |
| 32 | Struck pointing with cement mortar consisting one part cement and two part of sand including all complete. SI No. 578 |
| 33 | 75mm thick rubbed stone flooring over 20mm thick based of cement mortar 1:5 with join 3mm thick, side buttered with cement mortar 1:2 admixed with pigment to matched the shade of stone and pointing with same mortar. (Red Stone) |
| 34 | Plantation work around of pond |
| 35 | Excavation in foundation in ordinary soil (loamclay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth up to a distance of 30m. from the foundation trenches including all T&P. SI no.-251 |
| 36 | Providing and laying in Cement concrete 1:4:8 (1Cement:4 find sand :8 graded stone grit 40mm nominal size) and curing complete, including cost of formwork in foundation. SI No.-281 |
| 37 | M-150 brick work in 1:4 with cement coarse sand including all complete. SI No. 305b-309 |
| 38 | 75mm thick rubbed stone flooring over 20mm thick based of cement mortar 1:5 with join 3mm thick, side buttered with cement mortar 1:2 admixed with pigment to matched the shade of stone and pointing with same mortar. (Red Stone) |
| 39 | Saplings of Raystonea Regia Royal Palm Tree and feeling of fertilizer etc all complete. |