| 1 | Maintenance of Earthen Shoulder (filling with fresh soil) Making up loss of material / irregularities on shoulder to the design level by adding fresh approved soil and compacting it with appropriate equipment. (Average filling depth 150 mm),includingall labour, usage charges of machinery, lead, lifts, loading, unloading transporting etc., complete. |
| 2 | a) NH-169 |
| 3 | Providing repair to stone pitching/ apron over the filter media/ drainage layer at scattered locations over the slopes of guide bunds, river training works, and road embankments as per Technical Specifications Clause no. 2504 complete in all respects as directed by Engineer involving the below given operations however as per its actual applicability at site |
| 4 | a) NH-169 |
| 5 | Removal of earth from the choked hill side drain and disposing it on the valley side manually,includingall labour, lead, lifts, loading, unloading ,transporting etc., complete. |
| 6 | a) NH-169 |
| 7 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials by (Tractor) and stacking of serviceable material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness including all labour, hire charges of all machineries etc., complete (For new road) - In area of light jungle by Mechanical means. |
| 8 | a) NH-169 |
| 9 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm thick.Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2, includingcost of all materials, all labour, usage charges of machinery, lead, lifts, loading, unloading stacking,transporting etc., complete exepet lead for bitumen & emulsion. Grading II 13mm (Nominal size) and other items mentioned in Clause 3 of Section 7 of comtract agreement. |
| 10 | Km 2.48 to 25.75From 2.48 to 13.15 (2L)From Km 13.15 to 25.75 (IL) |
| 11 | a)For 6.91 Km (2 lane without paved shoulder) |
| 12 | a) For 12.60 Km ( Intermediate lane without paved shoulder ) |
| 13 | Km 25.75 to Km 53.775, Km 55.06 to km 60.00 and km 123.80 to 153.00 km |
| 14 | a) For 8.45Km (2lane withpaved shoulder) |
| 15 | b) For 24.515Km (2 lane without paved shoudler) |
| 16 | c) For 12.00Km (IL lane) |
| 17 | d) For 17.20Km (SL lane) |