| 1 | Breakdown/Emergency works |
| 2 | Replacement of burnt/ damaged jumpers and tightening of remaining Jumpers on the same tower. |
| 3 | Replacement of damaged disc insulators of Tension string. |
| 4 | Replacement of damaged disc insulators of Suspension string. |
| 5 | Restoration of snapped power conductor. Complete job including mid-span compression joint, laying of conductor, rough sagging, tensioning of conductor dead-end assembly etc upto span of 500 meter tension to tension point. |
| 6 | Restoration of snapped earth wire Complete job including mid-span compression joint, laying of earth wire, rough sagging, tensioning of earth wire dead-end assembly etc up to span of 500 meter tension to tension point. |
| 7 | Removal of trees if dropped on the transmission line in case the fault occurred. |
| 8 | Repairing of damaged moose conductor by using helical sleeve or bolted or by shorting method without lowering the conductor. |
| 9 | Emergency tower top checking in case if the fault not located from ground. |
| 10 | Providing of stay wire to the towers for it strengthening. (Complete Job). |
| 11 | Planned Works: |
| 12 | Checking and tightening of jumper including inserting/removal of temporary local earthing. (Complete Job). |
| 13 | Checking and tightening of vibration dampers (12 Nos. per circuit per tower) including inserting/removal of temporary local earthing. (Complete job). |
| 14 | Checking and tightening of corona rings (12 Nos. per circuit per tower) including inserting/removal of temporary local earthing. (Complete Job). |
| 15 | Replacement of damaged disc insulators of Tension string. |
| 16 | Replacement of damaged disc insulators of Suspension string. |
| 17 | Tightening of nuts and bolts of tower superstructures having tower weight from upto 20 tonnes. |
| 18 | Tightening of nuts and bolts of tower superstructures having tower weight more than 20 tonnes. |
| 19 | Replacement of damaged corona ring. |
| 20 | Replacement of Damaged or missing line spacers. |
| 21 | Fixing of anti-climbing device/Bird Guard over tower. |
| 22 | Checking and tightening of tower footing earthing bolt and measuring tower footing resistance. |
| 23 | Fixing of new vibration dampers on earthwire/ACSR moose conductor (including inserting/removal of temporary local earthing). |
| 24 | Replacement of damaged or missing tower members. |
| 25 | Branch cutting: Under the corridor of 400 KV D/C Baglihar Kishanpur transmission line 48 metre wide and under tower structure. |