| 1 | Repair to pot holes and removal of loose material, trimming of sides, cleaning of surface by providing tack coat, 20 mm thick pre-mix carpet and seal coat type B specificationClause 1904. |
| 2 | Providing, laying, spreading & compaction of stone aggregates of specific sizes to WBM specifications including spreading in uniform thickness, hand packing, rolling with power roller 8-10 tonn in stages to proper grade & camber, applying & brooming requisite type of screening / binding materials to fill up the intristices of coarse aggregates, watering & rolling making necessary earthen bund to protect edges lighting, guarding & barricatings & maintenance of diversions etc. [Grading of no-3] (22.4 - 53 mm size). |
| 3 | Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction |
| 4 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supplyofallmaterial, labour,T&P etc. required forproper completionof thework. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction |
| 5 | Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction |
| 6 | Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction. |
| 7 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 P.C.C1 :3:6 |
| 8 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 P.C.C. grade M 30 |
| 9 | Maintenance of DrainsThe maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1907. |
| 10 | Surface Drains in SoilConstruction of unlined surface drains of average cross-sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions. Excavated material to be used in embankment with a lift upto 3m and lead of 50 m (average lead 25 m) as per Technical Specification Clause 307. |
| 11 | Cleaning of fully choked scupper and catchpit complete as directed by the Engineer-in-charge. |
| 12 | Cleaning of partially choked scupper and catchpit complete as directed by the Engineer-in-charge. |
| 13 | Painting on Steel SurfacesProviding and applying two coats of ready mix paint including primer coat of approved brand on steel surface after through cleaning of surface to give an even shade as per drawing and Technical Specification Clause 1701 |