| 1 | Dismantling, Fabrication & erection from M.S. Plate in size 5 mm to 8 mmA.M.S. Pipe |
| 2 | B.M.S. Bends |
| 3 | C.TeeNipple |
| 4 | D.Cone & Reducer |
| 5 | E.Vessel |
| 6 | Patch work |
| 7 | Replacement & Erection of any size M.S. Pipe line upto 12” ( Readymade pipe ) |
| 8 | Replacement & Erection of any size M.S. Pipe line 14” to 24” ( Readymade pipe ) |
| 9 | Replacement & Erection of any size M.S. Pipe line above 28” ( Readymade pipe ) |
| 10 | Replacement & Erection of any size M.S. Flange |
| 11 | Replacement & Erection of any size M.S. Bends |
| 12 | Fabrication, erection & replacement of any size M.S. bend from M.S. Pipe upto 12” |
| 13 | Fabrication, erection & replacement of any size M.S. bend from M.S. Pipe above 12” |
| 14 | Fabrication, Erection & fitting of M.S. Cross from M.S. Pipe upto 6” |
| 15 | Hand Hole connection nipple in Fabricated Valve upto 10” complete with flange & blend |
| 16 | Replacement & Erection of any sizeValves Fitting |
| 17 | Fabrication, Erection of Reducer from any size. |
| 18 | Fabrication& Erection of any size Blind |
| 19 | Fabrication, Erection of any size Tee / Nipple having size 14 inch or below 14 inch size |
| 20 | Fabrication &Erection of any size Tee / Nipple having size above 14 inch size |
| 21 | EvaporatorBody Tube Dismantling ( Leaky tube dismantling, which found during hydraulic testing ). |
| 22 | Evaporator Body Tube Dismantling ( Complete dismantling of tubes of complete Calendria). |
| 23 | Evaporator Body Tube Fitting with Hydraulic testing ( Leaky tube Fitting, which found during hydraulic testing ). |
| 24 | Complete Evaporator Body Tube Fitting with Hydraulic testing ( Complete fitting of tubes of complete Calendria). |
| 25 | Juice Heater Tube Dismantling ( Leaky tube dismantling, which found during hydraulic testing ). |
| 26 | Juice Heater Tube Dismantling ( Complete dismantling of tubes of complete Calendria). |
| 27 | Juice Heater Tube Fitting with Hydraulic testing( Leaky tube fitting, which found during hydraulic testing ). |
| 28 | Juice Heater Tube Fitting with Hydraulic testing ( Complete fitting of tubes of complete Calendria). |
| 29 | Fabrication of bed and erection of Pump having20 H.P. or below 20 H.P. motor with Pump and it’s alignment. |
| 30 | Fabrication of bed and erection of Pump above 20 H.P. motor with Pump and it’s alignment. |
| 31 | Dismantling, Fabrication and Erection of Coil for any equipment |
| 32 | Fabrication and Erection of I.B.R. Pipe lines |
| 33 | Erection of I.B.R. Bends |
| 34 | Erection of I.B.R. Flanges |
| 35 | Erection of I.B.R. Valves |
| 36 | Replacement of Molasses tank worn out sheets |
| 37 | Dismantling and shifting of any type of Scrap Items in scrap yard |
| 38 | Labour supply (per day 8 hours basis) (a) Fitter |
| 39 | (b) Welder |
| 40 | (c) Khalasi |
| 41 | (d) Helper |
| 42 | C..I. /FRP cross (Readymade) fitting |
| 43 | Dismantling fabrication & erection of any size M.S. gutter |
| 44 | Dismantling, Fabrication & Erection of Sulphur Gas Coolers ( Dia-900mm x Height-1770 mm ) as per our existing size & design complete in all respect of Sulphur Furnace |
| 45 | Dismantling, Fabrication & Erection of Umbrella with staging as per our existing design of Evaporator body No. 4, Size- 3500 mm Dia. and Thk. 6 mm |
| 46 | Dismantling, Fabrication & Erection of Light & Heavy Filtrate Bottles (Dia-600mm x Height-1280 mm )as per our existing Size & design of Vaccum Filter |
| 47 | Dismantling, Fabrication & Erection of Stool rest on beam of Evaporator alongwith it’s leveling. |
| 48 | Replacement & Erection of S.S. Pipe having size upto 12 inch |
| 49 | Replacement & Erection of S.S. Readymade Flange having size upto 12 inch |
| 50 | Replacement & Erection of S.S. Readymade Bendhaving size upto 12 inch |
| 51 | Fabrication, erection and replacement of S.S. Bend from S.S. Pipe having size upto 12 inch. |