| 1 | Clearing and Grubbing Road Land Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. By Manual Means. In area of non-thorny jungle. |
| 2 | Excavation for Structures - Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out,construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.Upto 3 m depth Ordinary soil |
| 3 | Concrete with cement, coarse sand and 40 mm gauge stone ballast in proportion 1:4:8 in foundations and floors including supply of all material, labour and T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 |
| 4 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 Nominal mix 1:3:6 |
| 5 | Brick masonry work in cement mortar in foundation completeexcluding pointing and plastering as per drawing and technical specifications Clauses 600, 1202 & 1203 Brick masonry in 1:4 cement mortar |
| 6 | Providing concrete for plainconcrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203Nominal mix (1:2:4) |
| 7 | Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification Clauses 613.3 and 1204 |
| 8 | Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 9 | Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 (For height upto 5 m) R.C.C grade M 20 |
| 10 | Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 |
| 11 | Construction of Embankment with Material Obtained from Roadway Cutting Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 |
| 12 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1 |
| 13 | Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408 Using naturally occuring gravel |
| 14 | By Mix in Place Method - Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401 |
| 15 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. (By Mechanical Means with 1 km lead) |
| 16 | Brick on edge pavement with straight overburnt bricks laid on edgeincluding preparation of subgrade to prescribed camber and includingsupply of bricks, filling joints with local sand and spreading blinding coat1cm (3/8\") depth of local sand over the entire surface and including supplyof all materials, labour and T&P etc. required for proper completion of the work. |
| 17 | Tack coat using VG-10 grade bitumenOver granular surfaces treated with primer @ 0.40 kg/sqm |
| 18 | 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508. Case - I By Manual Means Bitumen (VG-30) |
| 19 | Seal Coat - Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 Case - II : Type B Bitumen (VG-30) |