| 1 | 1 | Excavation in foundation in all type of soil including lift 1.5 Mtr and lead 30 Mtr (As Per Direction E/I) | | 4 | M³ |
|---|
| 2 | 2 | P.C.C. in 1:4:8 Cement and coarse sand mortar 4 Cm gauge stone shingle/including supply of all material labour T & P etc. | | 8 | M³ |
|---|
| 3 | 3 | Ist Class B/W in 1:6 Cement fine sand mortar in foundation including supply of all material labour T&P etc. | | 4 | M³ |
|---|
| 4 | 4 | R.C.C Work in 1:1.1/2:3 Cement Coarse sand 2 Cm stone shingle/Grit including supply of all material labour, T&P etc. including centering and shuttering. | | 3 | M³ |
|---|
| 5 | 5 | M.S Tor steel in reinforcement including supply of all material labour T&P etc. Required for proper completion of the work. | | 6 | Qtl |
|---|
| 6 | 6 | Disposal of excavated earth /Malva/lime slakar with in 1 Km distance as directed by E/I | | 30 | M³ |
|---|
| 7 | 7 | 50 mm Thick CC floor 1:2:4 cement Coarse Sand, Stone single/grit including supply of all material labour T&P etc. | | 450 | Sq.Mtr |
|---|
| 8 | 8 | Dismantiling old and Wornout Plaster | | 200 | Sq.Mtr |
|---|
| 9 | 9 | Repairs to plaster of Thickness 12 mm To 20mm on Patches area including supply of all material labour T&P etc. Required for Proper Competition of the Work | | 100 | Sq.Mtr |
|---|
| 10 | 10 | 12 mm Thick plaster in 1:4 including supply of all material labour T&P etc | | 250 | Sq.Mtr |
|---|
| 11 | 11 | S/F of galvanized corrugated iron roof and side cleading 24 BWG old/new GCI sheet imposition including supply of all material 10 mm Dia J/L Hook of U bolt lump. Bitumen washer of approved quality but excluding cost of GCI Sheet provided by the factory. | | 350 | Sq.Mtr |
|---|
| 12 | 12 | White washing two coat including supply of all material labour T&P etc. | | 3500 | Sq.Mtr |
|---|
| 13 | 13 | Dismantiling old and Wornout heavy size iron work such as truss , purlins etc. upto 15 Mtr. Hight including supply of all material labour T&P etc. Required for Proper Completitionof the Work | | 1 | M.T. |
|---|
| 14 | 14 | M.S Work in heavy Size Fabrication and erection such as purline and gutter labour T&P etc.but excluding cost of S.Steel provided by the factory. | | 1 | M.T. |
|---|
| 15 | 15 | C.C Work in 1:2:4 Cement coarse sand and 2 cm stone single including supply of material labour T&P etc up to 6 Mtr height | | 14 | M³ |
|---|
| 16 | 16 | Snowcem work of approved quality two coat as per PWD specification including all material labour T&P etc. | | 4600 | Sq.Mtr |
|---|
| 17 | 17 | Oil bond Distemper two coat including supply of all material labour T&P etc. | | 2525 | Sq.Mtr |
|---|
| 18 | 18 | Painting or varnishing in Iron work or wood work two coat including supply of material labour T&P etc. | | 200 | Sq.Mtr |
|---|
| 19 | 19 | Providing pocket holes in foundation as per Drawing including cost of material | | 10 | Nos |
|---|
| 20 | 20 | Dismantling of old floor. Up to 50mm | | 220 | Sq.Mtr |
|---|
| 21 | 21 | Dismantling of GCI/A.C. sheets including labour T & P required for proper completion of work upto 15 Mtr height. | | 450 | Sq.Mtr |
|---|
| 22 | 22 | Demolishing cement mortar brick work manually/by mechanical means including stacking serviceable material and disposal of unserviceable material with in 50 Mtrs lead as per direction of E/I | | 4 | M³ |
|---|
| 23 | 23 | First class brick work 1:6 in super structure above plinth level up to floor v level in all shapes and sizes in cement motar 1:6 cement and coarse sand including supply of all materral labour T & P etc. (Except cost of bricks) required for proper completion of the work. | | 8 | M³ |
|---|
| 24 | 24 | Same as item No. ‘23’ above but including cost of bricks. | | 3 | M³ |
|---|
| 25 | 25 | S/F A.C Sheets 6 mm thick grey corrugated asbestas sheet (Charminar Make). including supply of all material labour,hook,bolt,Nut washer T & P etc. reuqired for the proper completion of the work and includion wastage. | | 200 | Sq.Mtr |
|---|
| 26 | 26 | Scraping oil boild distemper snowcem and lime or colour wash surface including material labour T & P etc. | | 1650 | Sq.Mtr |
|---|
| 27 | 27 | S/F of G.C.I. roof and side cleading 22 BWG inposition. Including supply of all material 10 mm Dia J/L hook, U Bolt, Bitumin and Lumpirwasher of approved quality. | | 200 | Sq.Mtr |
|---|
| 28 | 28 | Supply and laying Asian/Berger make Damp Proof Double Coat on Leakage roof after cleaning the roof surface. Including supply of all material Labour T & P etc. required for proper completin of the work. | | 450 | Sq.Mtr |
|---|
| 29 | 29 | Earth Work in Excavation by JCB machine. Including all labour, fuel, machine etc. required for proper completion of the work. | | 10 | Per hour |
|---|
| 30 | 30 | Earth filling in Road, foundation etc. with watering ramming and leveling. Including supply of all material labour T & P etc. required for proper completion of the work. | | 10 | M³ |
|---|
| 31 | 31 | Demolishing R.C.C. work manually. Incuding stacking of steel bars and disposal of unserviceable material with in the upto 1 Km lead as per direction of E/I | | 4 | M³ |
|---|
| 32 | 32 | Cleaning of drain near cane carrier to bullock cart gate boundary wall and disposal of unserviceable material with in upto 1 Km lead as per direction of E/I | | 1 | LS |
|---|
| 33 | 33 | Providing, Hoisting and fixing Precast R.C.C. Slab1:2:4. Including cost of required shuttering and centering but excluding the cost of peinforcement required for proper completion of the work. | | 6.4 | M³ |
|---|
| 34 | 34 | 52mm thick cement concrete flooring with concrete hardner topping under 50mm thick cement concrete1:2:4 and top layer 12mm thick cement hardner consisting of mix 1:2. Including supply of all material labour T & P etc. required for proper completion of the work. | | 250 | Sq.Mtr |
|---|
| 35 | 36 | Fixing G.C.I. Sheet, Including supply of hook, bolt nut, washer, labour T & P etc above 10 mtr height except cost of G.C.I. sheets. Including dismantling sheet. 10’ Long G.C.I. Sheet | | 1 | Nos |
|---|
| 36 | 37 | Fixing G.C.I. Sheet, Including supply of hook, bolt nut, washer, labour T & P etc above 10 mtr height except cost of G.C.I. sheets. Including dismantling sheet. 5’ to 8’ G.C.I. Sheet | | 1 | Nos |
|---|
| 37 | 39 | Supply and fixing A.C. Sheets 6mm thickness including supply of all material labour T & P etc above 10 Mtr height including dismantling sheet. 10’ Long A.C. Sheet | | 1 | Nos |
|---|
| 38 | 40 | Supply and fixing A.C. Sheets 6mm thickness including supply of all material labour T & P etc above 10 Mtr height including dismantling sheet. 5’ to 8’ Long A.C.Sheet | | 1 | Nos |
|---|
| 39 | 41 | Tiles work in flooring Size 2’ x 2’ | | 30 | Sq.Mtr |
|---|
| 40 | 42 | Tiles work in flooring Size 1’ x 1’ | | 20 | Sq.Mtr |
|---|
| 41 | 43 | Tiles work in walls Size 12” x 18” | | 25 | Sq.Mtr |
|---|
| 42 | 44 | Tiles work in walls Size 10” x 15” | | 30 | Sq.Mtr |
|---|
| 43 | 45 | P.O.P. Work in Roof (Ceiling) | | 20 | Sq.Mtr |
|---|
| 44 | 46 | Fall Ceiling in P.O.P | | 20 | Sq.Mtr |
|---|
| 45 | 47 | Wooden Work in Doors & Window Ply wood peneld & glazed including the cost of all fitting | | 20 | Sq.Mtr |
|---|
| 46 | 48 | Ist Class Brick Work in Foundation & Plinth | | 5 | CM² |
|---|
| 47 | 49 | Brick Flroring with sand | | 5 | Sq.Mtr |
|---|
| 48 | 50 | 75 x 75 mm cement sand gola in joint of parpit wall & roog. | | 50 | R.Mtr |
|---|