| 1 | 0.05 | DESCRIPTION OF ITEMS | | | |
|---|
| 2 | 1 | Disconnecting / taking down carefully ceiling fan from existing position, dismantling, overhauling and cleaning throughly, oiling / greasing and rehanging at same or new locations after replacing split pins, check nuts, rubber seal etc and re-assemble duly connected with new PVC three core flexible copper conductor cable of size 23/.0076, complete testing & specified all as directed. Note: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 100 | Each\nJob |
|---|
| 3 | 2 | M & L for taking out burnt copper winding from Ceiling Fan of 1200 mm size and rewinding with existing /same guage of super enammeled copper winding wire complete all as specified and directed. | | 30 | Each\nJob |
|---|
| 4 | 3 | Supply only Ball bearing for Ceiling fan | | 50 | Each |
|---|
| 5 | 4 | Supply only Capacitor 2.5 Mfd +- 5% 440 Volt AC 50 Hz | | 80 | Each |
|---|
| 6 | 5 | Disconnecting / taking down carefully Exhaust Fan of any size from existing position, dismantling, overhauling and cleaning throughly, oiling /greasing and rehanging after replacing split pins , check nuts, rubber seal bushes etc and re- assemble duly connected with new PVC three core flexible copper conductor cable of size 23/.0076, complete testing & specified all as directed. \nNote: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 50 | Each\nJob |
|---|
| 7 | 6 | M & L for taking out burnt copper winding from exhaust Fan of any size/type and rewinding with existing /same guage of super enammeled copper wire complete all as specified and directed | | 25 | Each\nJob |
|---|
| 8 | 7 | Supply only Capacitor 4 Mfd +/- 5% 440 Volt AC 50 Hz | | 40 | Each |
|---|
| 9 | 8 | Supply only Capacitor 15 Mfd +/- 5% 440 Volt AC 50 Hz | | 10 | Each |
|---|
| 10 | 9 | Taking down carefully storage water heater of capacity up to 25/35/50 ltr dismantling inner tank and outer tank, pipe assembly, cleaning throughly with descalling liquid compound, overhauling complete to ensure free and constant flow of water through outlet, welding of inner tank if required at site rethreading of inlet/outlet pipe 15 mm dia, reassembling the same at existing /new location including necessary fasteners to ensure proper safety as reqd at site, testing and commissioning after re-installation at site complete all as specified and directed. \nNote: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 10 | Each \nJob |
|---|
| 11 | 10 | Supply only thermostate fitting fitment varying capacity for 25/35/50ltrs capacity geysers | | 10 | Each |
|---|
| 12 | 11 | Supply only PVC connection pipe nylon threaded 15mm size with brass nuts copping in both end of length 450mm for geysers | | 10 | Each |
|---|
| 13 | 12 | Supply only heating element of 1.5/2.0 KW for geyser (as per sample ISI brand) | | 20 | Each |
|---|
| 14 | 13 | Taking down carefully flate-plate solar collector storage solar water heater of capacity up to 100 ltr dismantling inner tank and outer tank, pipe assembly, cleaning throughly with descalling liquid compound, overhauling complete to ensure free and constant flow of water through outlet , welding of inner tank if required at site, laser/ultrasonic welding for bonding fin and raiser tube, repair of copper bracing for bonding of header and raiser making leak proof, repair & repalcement of back and side insulation material, rethreading of inlet/outlet pipe 20mm dia, reassembling the same at existing location including necessary fasteners to ensure proper safety as reqd at site, repair / welding of MS structure for collector stand, testing and commissioning after re-installation at site complete all as specified and directed. \nNote: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 10 | Each Job |
|---|
| 15 | 14 | Checking of fault in Solar water Heater by deputing adequate number of qualified Solar technician/Plumber and helper with necessary T&P and safety tools etc and ensure that to restore water heater in working condition after rectifying the fault with using minor items of cost not more than Rs. 10/- shall be included in the quoted unit rate, complete all as specified and directed.\nNote:- (a) Replacement of solar heater items, if required shall be measured and paid separetely in relevant items. Unserviceable items retrived form complaints shall be abstracted under sch of credit.\n(b) The fault shall be attended within one day, otherwise recovery shall be charged Rs. 50/- per complaint per day. \n(c) Electrician and plumber shall obtain the complaint slip from JE EM and the same will be depositing to JE EM duly signed by Users after completing the job for making payments. | | 30 | Each Job |
|---|
| 16 | 15 | Supply only Heating element 3 KW for solar water heater (as per sample ISI brand) | | 15 | Each |
|---|
| 17 | 16 | Supply only Thermostat for solar water heater 100 Ltr | | 20 | Each |
|---|
| 18 | 17 | Supply only flate-plate solar collector transparent cover to prevent heat loss and made with ironpoor solar safety toughened glass, 4 mm thick with low iron, transmissivity upto 92% at near normal incidence glass as same as existing | | 10 | Each |
|---|
| 19 | 18 | Supply only Selective black chrome electroplated absorber plate fin made with Electro grade copper with 99.9% with an absorber coating of selective black chrome electroplated, to withstand 300 degree centigrade of size suitable with existing collector plate | | 5 | Each |
|---|
| 20 | 19 | Supply only insulating material for flate-plate solar collector water heating system made with Rock wool/ Mineral wool/ Fibre Glass wool with 48Kg/cu.mt density for better heat prevention | | 6 | Kg |
|---|
| 21 | 20 | Supply only Heavy duty nylon threaded flexible PVC/CPVC connection pipe 25mm dia suitable for both hot & cold water | | 100 | RM |
|---|
| 22 | 21 | Supply only GI/brass adjustable scew clamp as per sample | | 100 | Each |
|---|
| 23 | 22 | M & L for sub main wiring with 2 runs of 4 Sqmm and one runs of 4 Sqmm Copper cable FRLS multistranded drawn in and including PVC conduit in walls / surface providing necessary clamps, screws, thimbles and connected to MCB of solar water heater / DB box etc all as reqd at site complte specified and directed.\nNote: 1. Three runs of 4 Sqmm and one run of PVC conduit shall be measured as one unit. \n2. Cost of cutting chasing and making good of surface shall be deemed included in quoted unit rate. | | 750 | RM |
|---|
| 24 | 23 | Supply only Makeup tank for solar water heater 250 Ltr | | 1 | Each |
|---|
| 25 | 24 | Supply only Elbow 15mm | | 5 | Each |
|---|
| 26 | 25 | Supply only Tee 15mm | | 5 | Each |
|---|
| 27 | 26 | Supply only Socket 15 mm | | 5 | Each |
|---|
| 28 | 27 | Supply only Union 15mm | | 5 | Each |
|---|
| 29 | 28 | Supply only Reducer Socket 20 mm | | 5 | Each |
|---|
| 30 | 29 | Supply only Tank nipple 15 mm | | 5 | Each |
|---|
| 31 | 30 | Supply only Nipple 15 mm | | 10 | Each |
|---|
| 32 | 31 | Supply only Butterfly valve 15mm | | 5 | Each |
|---|
| 33 | 32 | Supply only M-Seal | | 1 | Kg |
|---|
| 34 | 33 | S & F in repair Tank lid 200 ltrs | | 10 | Each |
|---|
| 35 | 34 | S & F in repairs 15 mm bore medium grade galvanised steel tubing with all fittings and fixed complete to walls and ceiling or laid in floor including taking down complete all as specified and directed. | | 12 | RM |
|---|
| 36 | 35 | S & F in repairs 20 mm bore medium grade galvanised steel tubing with all fittings and fixed complete to walls and ceiling or laid in floor including taking down complete all as specified and directed. | | 12 | RM |
|---|
| 37 | 36 | S & F in repairs Gun Metal gate valve with Iron wheel head screwed both ends for GI steel tubing 20mm dia including taking down unserviceable valve complete all as specified and directed. | | 5 | Each |
|---|
| 38 | 37 | S & F in repairs 20mm bore dia of pipe Ball valves high pressure of PTMT with epoxy coated aluminium rod & high density plastic ball screwed for iron pipe and fixed (minimum weight 20mm -210 gms )complete all as specified and directed. | | 35 | Each \n |
|---|
| 39 | 38 | Taking down carefully Evacuated tube collector storage solar water heater of capacity up to 250 ltr dismantling inner tank and outer tank, pipe assembly, cleaning throughly with descalling liquid compound, overhauling complete to ensure free and constant flow of water through outlet, welding of inner tank if required at site, repair/replacement of evacuated tube with rubber washers & copper pipe, heat fin etc, repair & repalcement of insulation material, rethreading of inlet/outlet pipe 20 mm dia, reassembling the same at existing location including necessary fasteners to ensure proper safety as reqd at site, repair / welding of MS structure for collector stand, testing and commissioning after re-installation at site complete all as specified and directed.\nNote: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 5 | Each |
|---|
| 40 | 39 | Supply only evacuated tube for solar water heating system with proper heat absorber selective chrome coating of size 1800mm x 58 mm dia or as existing size with in built heat exchanger copper pipe including end caps and rubber washers suitable for connecting with the existing manifold | | 10 | Each |
|---|
| 41 | 40 | Supply only insulating material Polyurethene Foam or as same as existing for proper heat protection | | 5 | Kg |
|---|
| 42 | 41 | Taking down carefully self container drinking water cooler storage capacity upto 150 Lts dismantling inner tank and outer tank, pipe assembly, cleaning throughly with descalling liquid compound, overhauling complete to ensure free and constant flow of water through outlet , welding of inner tank if required at site rethreading of inlet/outlet pipe 15mm dia, through checking/ rectification of fault in electrical circuits and refrigeration system, oiling & graesing of blower motor, replacement of compressor/ blower or other necessary parts as required, reassembling the same at existing / new location including necessary fasteners to ensure proper safety as reqd at site, testing and commissioning after re-installation at site complete all as specified and directed. \nNote: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 10 | Each |
|---|
| 43 | 42 | Supply only Compressor unit with all connected accessories of existing size/rating for water cooler storage capacity upto 150 Ltrs | | 2 | Each |
|---|
| 44 | 43 | Supply only starting Capacitor suitable (As per sample) for water cooler capacity upto 150ltrs | | 6 | Each |
|---|
| 45 | 44 | Supply only running Capacitor suitable(As per sample) for water cooler capacity upto 150ltrs | | 6 | Each |
|---|
| 46 | 45 | Supply only Relay assembly ffor water cooler capacity upto 150ltrs | | 5 | Each |
|---|
| 47 | 46 | Supply only thermostate unit for storage type water cooler of capacity upto 50ltrs | | 5 | Each |
|---|
| 48 | 47 | Supply only over load protection for water cooler | | 5 | Each |
|---|
| 49 | 48 | Supply only blower motor of suitable size for water cooler capacity upto 150ltrs | | 1 | Each |
|---|
| 50 | 49 | Supply only Fan blade of suitable size for water cooler capacity upto 150ltrs | | 1 | Each |
|---|
| 51 | 50 | M & L for taking out burnt copper winding of blower motor of water cooler Capacity upto 150 Ltr and refixing after rewinding blower motor, testing after complete all as reqd at site complete all as specified and directed | | 3 | Each |
|---|
| 52 | 51 | Cutting suction and discharge gas pipeline and taking out unserviceable compressor unit from refrigerator of 165/175/195 ltrs capacity and S&F new sealed compressor unit of same model or approved model of same capacity complete including commissioning and testing after installation at site complete all as specified and directed | | 1 | Each \nJob |
|---|
| 53 | 52 | All as per item No 51 above but for refrigerator of capacity 280/310 Ltrs | | 1 | Each \nJob |
|---|
| 54 | 53 | S & F in repair of cooling coil and housing of refrigerator unit of any make and capacity upto 310 lts | | 2 | Each |
|---|
| 55 | 54 | S & F in repair relay assembly and OLP for Refrigerator, storage Capacity 165/285/310 Ltr (As per sample) including taking down old defective one complete all as specified and directed | | 8 | Each |
|---|
| 56 | 55 | S & F in repair thermostate unit for Refrigerator suitable for capacity 165/195/285/310 Ltr (As per sample) including taking down old defective thermostate unit complete all as specified and directed. | | 7 | Each |
|---|
| 57 | 56 | S & F in repair door Gasket for refrigerator of capacity upto 310ltrs(As per sample) including taking down old door gasket and allignment of door after opening from body including inserting packing, welding, threading, etc what so ever required to leave no air gap between door and body and top edge of Refrigerator flushing with top surface of refrgerator all as specified and directed | | 6 | Each |
|---|
| 58 | 57 | Supply and joint new capillary for charging refrigerent gas in machine including taking down unserviceable capillary from any capacity refrigerator complete all as specified and directed. | | 5 | Each |
|---|
| 59 | 58 | M & L for Charging with suitable Refrigerant Gas R-134(a) after cutting opening sealed unit (compressor) of water Cooler / Refrigerator of any size / capacity / type including replacement of capliary pipe and moisture driver filter etc including crimping and re-soldering to charging line complete all as reqd at site complete specified and directed. | | 7 | Each \nJob |
|---|
| 60 | 59 | Disconnecting all electrical and copper pipe connection and taking down carefully AC of any type/ rating (window/split) from existing position, dismantling, servicing, overhauling and cleaning of filters, fans, indoor and outdoor units through washing or air pressure throughly, checking cooling coil, compressor, gas level, oiling and greasing of fan & motor etc and re install at same locations after replacing defective parts duly connected with existing AC supply complete all as reqd at site,specified and directed\nNote: 1. Replacement of unserviceable parts if required, shall be measured and paid as under supply only separetely in relevant items. \n2. Unserviceable items retrived form this item shall be abstracted under sch of credit. | | 7 | Each Job |
|---|
| 61 | 60 | Supply only starting relay for 1.5 TR capacity AC of existing make | | 3 | Each |
|---|
| 62 | 61 | Supply only starting capacitor 80-100Mfd for 1.5 TR capacity AC of existing make | | 3 | Each |
|---|
| 63 | 62 | Supply only running capacitor 36 Mfd for 1.5 TR capacity AC of any make/Type | | 3 | Each |
|---|
| 64 | 63 | Supply only condensor fan motor for split AC 1.5 TR capacity AC (as per sample) | | 1 | Each |
|---|
| 65 | 64 | Supply only thermostate unit including electronic relay eqpt and electronic plate for 1.5 TR capacity AC | | 2 | Each |
|---|
| 66 | 65 | M & L for Charging with suitable Refrigerant Gas R-32/R-410(A) after cutting opening sealed unit (compressor) of AC of any type and capacity upto 1.5 TR including replacement of capliary pipe and moisture driver filter etc including crimping and re soldering to charging line complete all as reqd at site complete all as specified and directed | | 3 | Each \nJob |
|---|