| 1 | 1 | Key personnel | BI01010001010000000000000515BI0100001112 | | |
|---|
| 2 | 1.01 | Team Leader Cum Senior Highway Engineer | BI01010001010000000000000515BI0100001113 | 9 | man month |
|---|
| 3 | 1.02 | Senior bridge Engineer | BI01010001010000000000000515BI0100001114 | 5 | man month |
|---|
| 4 | 1.03 | Highway cum Pavement Engineer | BI01010001010000000000000515BI0100001115 | 5 | man month |
|---|
| 5 | 1.04 | Material-cum-Geo-technical Engineer – Geologist | BI01010001010000000000000515BI0100001116 | 6 | man month |
|---|
| 6 | 1.05 | Senior Survey Engineer | BI01010001010000000000000515BI0100001117 | 7 | man month |
|---|
| 7 | 1.06 | Traffic and Safety expert | BI01010001010000000000000515BI0100001118 | 4 | man month |
|---|
| 8 | 1.07 | Environmental Specialist | BI01010001010000000000000515BI0100001119 | 3 | man month |
|---|
| 9 | 1.08 | Quantity Surveyor / Documentation Expert | BI01010001010000000000000515BI0100001120 | 6 | man month |
|---|
| 10 | 1.09 | Land Acquisition Expert | BI01010001010000000000000515BI0100001121 | 10 | man month |
|---|
| 11 | 1.1 | Utility Expert | BI01010001010000000000000515BI0100001122 | 4 | man month |
|---|
| 12 | 1.11 | Tunnel Design Expert | BI01010001010000000000000515BI0100001123 | 10 | man month |
|---|
| 13 | 1.12 | Senior Geophysicist | BI01010001010000000000000515BI0100001124 | 6 | man month |
|---|
| 14 | 1.13 | Senior Geotechnical Engineer | BI01010001010000000000000515BI0100001125 | 10 | man month |
|---|
| 15 | 1.14 | Senior E&M Expert | BI01010001010000000000000515BI0100001126 | 6 | man month |
|---|
| 16 | 1.15 | Senior Geologist | BI01010001010000000000000515BI0100001127 | 10 | man month |
|---|
| 17 | 2 | Sub Professional Staff\n(To be assessed by consultant as per requirement of assignment and one sub-professional be a fresh graduate) Name and position to be filled in below columns by the bidder | BI01010001010000000000000515BI0100001128 | | |
|---|
| 18 | 2.01 | Position | BI01010001010000000000000515BI0100001129 | 1 | LS |
|---|
| 19 | 2.02 | Position | BI01010001010000000000000515BI0100001130 | 1 | LS |
|---|
| 20 | 2.03 | Position | BI01010001010000000000000515BI0100001131 | 1 | LS |
|---|
| 21 | 2.04 | Position | BI01010001010000000000000515BI0100001132 | 1 | LS |
|---|
| 22 | 2.05 | Position | BI01010001010000000000000515BI0100001133 | 1 | LS |
|---|
| 23 | 2.06 | Position | BI01010001010000000000000515BI0100001134 | 1 | LS |
|---|
| 24 | 2.07 | Position | BI01010001010000000000000515BI0100001135 | 1 | LS |
|---|
| 25 | 3 | Support staff\nNote: To be assessed by consultant as per requirement of assignment | BI01010001010000000000000515BI0100001136 | | |
|---|
| 26 | 3.01 | Office Manager | BI01010001010000000000000515BI0100001137 | 10 | man month |
|---|
| 27 | 3.02 | Typist | BI01010001010000000000000515BI0100001138 | 10 | man month |
|---|
| 28 | 3.03 | Office Boy | BI01010001010000000000000515BI0100001139 | 10 | man month |
|---|
| 29 | 3.04 | Night Watchman | BI01010001010000000000000515BI0100001140 | 10 | man month |
|---|
| 30 | 4 | Transportation | BI01010001010000000000000515BI0100001141 | | |
|---|
| 31 | 4.01 | The vehicles provided by the Consultants shall\ninclude the cost for rental, drivers, operation,\nmaintenance, repairs, insurance, etc.\nA. For use of consultants \n | BI01010001010000000000000515BI0100001142 | 10 | Month |
|---|
| 32 | 5 | Duty travel to site (Fixed costs) | BI01010001010000000000000515BI0100001143 | 1 | LS |
|---|
| 33 | 6 | Office rent (Fixed costs)\n(The rent cost includes maintenance, cleaning, repairs, etc. ) | BI01010001010000000000000515BI0100001144 | 10 | Month |
|---|
| 34 | 7 | Office supplies, Utilities and Communication (Fixed Costs) | BI01010001010000000000000515BI0100001145 | | |
|---|
| 35 | 7.01 | Office Supplies Drafting | BI01010001010000000000000515BI0100001146 | 10 | Month |
|---|
| 36 | 7.02 | Supplies Computer | BI01010001010000000000000515BI0100001147 | 10 | Month |
|---|
| 37 | 7.03 | Running Costs | BI01010001010000000000000515BI0100001148 | 10 | Month |
|---|
| 38 | 7.04 | Domestic and International Communication | BI01010001010000000000000515BI0100001149 | 10 | Month |
|---|
| 39 | 8 | Office furniture and Equipments (Rental) | BI01010001010000000000000515BI0100001150 | 1 | LS |
|---|
| 40 | 9 | Reports and Document Printing | BI01010001010000000000000515BI0100001151 | | |
|---|
| 41 | 9.01 | Monthly Report (per month) | BI01010001010000000000000515BI0100001152 | 3 | Nos |
|---|
| 42 | 9.02 | Inception Report & QAP | BI01010001010000000000000515BI0100001153 | 5 | Nos |
|---|
| 43 | 9.03 | Environment and Social Impact Screening Report \n | BI01010001010000000000000515BI0100001154 | 5 | Nos |
|---|
| 44 | 9.04 | Draft Feasibility Report | BI01010001010000000000000515BI0100001155 | 5 | Nos |
|---|
| 45 | 9.05 | Final Feasibility Report | BI01010001010000000000000515BI0100001156 | 6 | Nos |
|---|
| 46 | 9.06 | Strip Plan with L.A. Reports | BI01010001010000000000000515BI0100001157 | 6 | Nos |
|---|
| 47 | 9.07 | Draft LA and Clearances I Report | BI01010001010000000000000515BI0100001158 | 5 | Nos |
|---|
| 48 | 9.08 | Final LA and Clearances I Report | BI01010001010000000000000515BI0100001159 | 5 | Nos |
|---|
| 49 | 9.09 | Draft Environmental Assessment report & RAP | BI01010001010000000000000515BI0100001160 | 5 | Nos |
|---|
| 50 | 9.1 | Final Environmental Assessment report & RAP | BI01010001010000000000000515BI0100001161 | 6 | Nos |
|---|
| 51 | 9.11 | Draft Detailed Design Report & Drawings etc. | BI01010001010000000000000515BI0100001162 | 5 | Nos |
|---|
| 52 | 9.12 | Draft EMP | BI01010001010000000000000515BI0100001163 | 5 | Nos |
|---|
| 53 | 9.13 | Draft Bidding Documents | BI01010001010000000000000515BI0100001164 | 5 | Nos |
|---|
| 54 | 9.14 | Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings etc. | BI01010001010000000000000515BI0100001165 | 6 | Nos |
|---|
| 55 | 9.15 | Final EMP | BI01010001010000000000000515BI0100001166 | 6 | Nos |
|---|
| 56 | 9.16 | Final Bidding Documents | BI01010001010000000000000515BI0100001167 | 6 | Nos |
|---|
| 57 | 9.17 | Draft 3(a) ,3(A) and 3(D) notification/ or equivalent publication as per NH Act / or State Act / or prevailing LA Act of area under consideration for land acquisition ( 3 copies each) \n | BI01010001010000000000000515BI0100001168 | 9 | Nos |
|---|
| 58 | 9.18 | LA & Clearances II Report | BI01010001010000000000000515BI0100001169 | 6 | Nos |
|---|
| 59 | 10 | Survey and Investigation | BI01010001010000000000000515BI0100001170 | | |
|---|
| 60 | 10.01 | A. Topographical Survey (Fixed Rate) | BI01010001010000000000000515BI0100001171 | | |
|---|
| 61 | 10.02 | Topographic Survey including hire charges for\nequipment and supply of survey teams comprising of\nproject survey filed staff etc. inclusive of cost of\nmaterials, labourer \n | BI01010001010000000000000515BI0100001172 | 48.2 | Km |
|---|
| 62 | 10.03 | Detailed topographic surveys using mobile/ aerial\nLiDAR or better technology | BI01010001010000000000000515BI0100001173 | 48.2 | Km |
|---|
| 63 | 10.04 | B. Investigation (Fixed cost) | BI01010001010000000000000515BI0100001174 | | |
|---|
| 64 | 10.05 | Road and Bridge Inventory | BI01010001010000000000000515BI0100001175 | 1 | LS |
|---|
| 65 | 10.06 | FWD Test and Pavement Evaluation | BI01010001010000000000000515BI0100001176 | 1 | LS |
|---|
| 66 | 10.07 | Roughness Survey | BI01010001010000000000000515BI0100001177 | 1 | LS |
|---|
| 67 | 10.08 | Axle Load Survey | BI01010001010000000000000515BI0100001178 | 1 | LS |
|---|
| 68 | 10.09 | Material Survey and Investigation | BI01010001010000000000000515BI0100001179 | 1 | LS |
|---|
| 69 | 10.1 | Sub-grade Investigation | BI01010001010000000000000515BI0100001180 | 1 | LS |
|---|
| 70 | 10.11 | Traffic Survey | BI01010001010000000000000515BI0100001181 | 1 | LS |
|---|
| 71 | 10.12 | Socio-economic & Census Survey/Studies | BI01010001010000000000000515BI0100001182 | 1 | LS |
|---|
| 72 | 10.13 | Land Acquisition Studies | BI01010001010000000000000515BI0100001183 | 1 | LS |
|---|
| 73 | 10.14 | Any other investigations/surveys | BI01010001010000000000000515BI0100001184 | 1 | LS |
|---|
| 74 | 10.15 | Sub-Soil Investigation (Boring) | BI01010001010000000000000515BI0100001185 | | |
|---|
| 75 | 10.16 | Boring in all type of soils (other than hard rock) \n1500m (for projects of length < 110 km) or 2000m (for projects of length > 110 km) \n | BI01010001010000000000000515BI0100001186 | 1500 | meter |
|---|
| 76 | 10.17 | Boring in hard rock\n200m (for projects of length < 110 km) or 300m (for projects of length > 110 km) \n | BI01010001010000000000000515BI0100001187 | 200 | meter |
|---|
| 77 | 10.18 | Boring for tunnel as per Annexure-I and S/No 13 of supplement-I | BI01010001010000000000000515BI0100001188 | 200 | meter |
|---|
| 78 | 11 | C. Net Work Survey and GPR | BI01010001010000000000000515BI0100001189 | | |
|---|
| 79 | 11.01 | Net work Survey of the existing Highways as a\nrepository for civil work as per directions from\nAuthority. \n | BI01010001010000000000000515BI0100001190 | 1 | Job |
|---|
| 80 | 11.02 | GPR Survey for detection of under ground utilities | BI01010001010000000000000515BI0100001191 | 1 | Job |
|---|
| 81 | 12 | Cost of supply and fixing Boundary Pillars | BI01010001010000000000000515BI0100001192 | | |
|---|
| 82 | 12.01 | Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967: Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval. (lumpsum ) \n | BI01010001010000000000000515BI0100001193 | 1 | LS |
|---|
| 83 | 13 | Land Acquisition Team including support staff and logistics/ transportation | BI01010001010000000000000515BI0100001194 | | |
|---|
| 84 | 13.01 | A. Land acquisition Team including support staff | BI01010001010000000000000515BI0100001195 | | |
|---|
| 85 | 13.02 | Ex-Land Revenue Inspector/Officer or equivalent \n | BI01010001010000000000000515BI0100001196 | 8 | Man month |
|---|
| 86 | 13.03 | Ex-Kanoogo/ Girdwar or equivalent | BI01010001010000000000000515BI0100001197 | 8 | Man month |
|---|
| 87 | 13.04 | Ex-Patwari or equivalent | BI01010001010000000000000515BI0100001198 | 8 | Man month |
|---|
| 88 | 13.05 | Typist | BI01010001010000000000000515BI0100001199 | 16 | Man month |
|---|
| 89 | 13.06 | Peon | BI01010001010000000000000515BI0100001200 | 8 | Man month |
|---|
| 90 | 13.07 | B. Logistics for Land acquisition Team | BI01010001010000000000000515BI0100001201 | | |
|---|
| 91 | 13.08 | Computer including necessary peripherals | BI01010001010000000000000515BI0100001202 | 16 | Man month |
|---|
| 92 | 13.09 | Printers | BI01010001010000000000000515BI0100001203 | 16 | Man month |
|---|
| 93 | 13.1 | Vehicles (Bolero or equivalent) with monthly running limit of 4000 km | BI01010001010000000000000515BI0100001204 | 8 | Man month |
|---|