| 1 | 1 | Fabrication & Erection | 1 | 11400 | Kilogram |
|---|
| 2 | 2 | Installaion of JBs & Local Consoles | 2 | 150 | Each |
|---|
| 3 | 3 | Installation of Switches, P.Bs, MCBs etc | 3 | 30 | Each |
|---|
| 4 | 4 | Relocation of JBs & Local Consoles | 4 | 50 | Each |
|---|
| 5 | 5 | Installation of Process Connections | 5 | 36 | Each |
|---|
| 6 | 6 | Cleaning Of Field Instruments | 6 | 6855 | Each |
|---|
| 7 | 7 | Work Assistance-1hour-1skill+1unskill | 7 | 900 | Each |
|---|
| 8 | 8 | Laying Of GI/MS Pipes up to 2\" | 8 | 105 | Meter |
|---|
| 9 | 9 | Laying Of Impulse Pipes upto 12mm | 9 | 189 | Meter |
|---|
| 10 | 10 | Conditioning of Cable Trays(Ex.raceways) | 10 | 6000 | Meter |
|---|
| 11 | 11 | Dressing of cables & heat protection | 11 | 1200 | Meter |
|---|
| 12 | 12 | Laying of cables: up to 5 cores(1.5/2.5) | 12 | 11250 | Meter |
|---|
| 13 | 13 | Laying of cables: more than 5 cores | 13 | 5250 | Meter |
|---|
| 14 | 14 | Data & Communication cable less than 1.5 | 14 | 750 | Meter |
|---|
| 15 | 15 | Cable jointing of all sizes | 15 | 75 | Each |
|---|
| 16 | 16 | Painting of instrument panel/LCB/JB etc | 16 | 1500 | Square Foot |
|---|
| 17 | 17 | Calibration assistance for weigh scale | 17 | 150 | Each |
|---|
| 18 | 18 | Pipe fitting: T/elbow/nipples etc. | 18 | 375 | Each |
|---|
| 19 | 19 | Cleaning of PLC/Control room panels. | 19 | 1050 | Each |
|---|
| 20 | 20 | Work Assistance by 1 Semi-Skilled Man | 20 | 5250 | Each |
|---|
| 21 | 21 | Installation Of Heavy field Instruments | 21 | 300 | Each |
|---|
| 22 | 22 | Installation of medium Field Instruments | 22 | 150 | Each |
|---|
| 23 | 23 | Installation of small field instruments | 23 | 300 | Each |
|---|
| 24 | 24 | Installation of Panel Instruments | 24 | 135 | Each |
|---|
| 25 | 25 | Installation of HMI/Panel View | 25 | 60 | Each |
|---|
| 26 | 26 | Checking/Replacement of devices in FTA | 26 | 75 | Each |
|---|
| 27 | 27 | Replacement of Pneumatic conveying inst | 27 | 60 | Each |
|---|
| 28 | 28 | Installation with fixture: photocell | 28 | 150 | Each |
|---|
| 29 | 29 | Replacement of workstation/HMI/SCADA | 29 | 75 | Each |
|---|
| 30 | 30 | Repair of raceways | 30 | 60 | Meter |
|---|
| 31 | 31 | Soldering of sockets with terminal insul | 31 | 225 | Each |
|---|
| 32 | 32 | Laying of cables and soldering of socket | 32 | 75 | Meter |
|---|
| 33 | 33 | Checking/changing of insulation only | 33 | 75 | Each |
|---|
| 34 | 34 | Termination of Burner ramp end only | 34 | 150 | Each |
|---|
| 35 | 35 | Repair of Burner Ramps | 35 | 15 | Each |
|---|
| 36 | 36 | Repairing of doors and cover of panels | 36 | 150 | Each |
|---|
| 37 | 37 | Arresting air and oil leackages | 37 | 90 | Each |
|---|
| 38 | 38 | Installation/Shifting panel: up to 25 kg | 38 | 150 | Each |
|---|
| 39 | 39 | Installation/Shifting panel:25 to 200 kg | 39 | 150 | Each |
|---|
| 40 | 40 | Installation/Shifting:200 to 500 kg | 40 | 150 | Each |
|---|
| 41 | 41 | Fabrication of Thermocouple | 41 | 6000 | Each |
|---|
| 42 | 42 | Calibration of paddle flow meter | 42 | 15 | Each |
|---|
| 43 | 43 | Calibration of belt weigher system | 43 | 30 | Each |
|---|
| 44 | 44 | Calibration/Simulation of Control Valve | 44 | 48 | Each |
|---|
| 45 | 45 | Maintenance of explosion vent at FTC/BF | 45 | 150 | Each |
|---|
| 46 | 46 | Maintenance of lubrication flow switch | 46 | 36 | Each |
|---|
| 47 | 47 | Simulation of flow control control ckt | 47 | 45 | Each |
|---|
| 48 | 48 | Maintenance of vibration sensors/Tx | 48 | 150 | Each |
|---|
| 49 | 49 | Simulation of Wireless devices of R/S | 49 | 45 | Each |
|---|
| 50 | 50 | Repair/Re-installaion of Belt Weigher | 50 | 30 | Each |
|---|
| 51 | 51 | Calibration of belt weigher system in CB | 51 | 30 | Each |
|---|
| 52 | 52 | Simulation of Pulsing/purging of DDU | 52 | 120 | Each |
|---|
| 53 | 53 | Calibration of level measurement circuit | 53 | 15 | Each |
|---|
| 54 | 54 | Configuration of Pump control circuit | 54 | 30 | Each |
|---|
| 55 | 55 | Simulation of speed control circuit | 55 | 24 | Each |
|---|
| 56 | 56 | Simulation of position control syst_SCM | 56 | 24 | Each |
|---|
| 57 | 57 | Calibration of Solidflow measurement sys | 57 | 12 | Each |
|---|
| 58 | 58 | Configuration of humidity meter in dryer | 58 | 30 | Each |
|---|
| 59 | 59 | Refurbishing/Installation of encoders | 59 | 30 | Each |
|---|
| 60 | 60 | Refurbishing/Installation of HFO flw mtr | 60 | 15 | Each |
|---|
| 61 | 61 | Refurbishing/Installation of Servo motor | 61 | 150 | Each |
|---|
| 62 | 62 | Refurbishing/Calibration of Servo motor | 62 | 120 | Each |
|---|
| 63 | 63 | Configuration/simulation_wireless comm | 63 | 24 | Each |
|---|
| 64 | 64 | Config/simulation of Temp.control loops | 64 | 60 | Each |
|---|
| 65 | 65 | Checking/simulation of com.networks | 65 | 30 | Each |
|---|
| 66 | 66 | Repair/Overhauling Instruments/Devices | 66 | 15 | Each |
|---|
| 67 | 67 | Configuration/simulation of Telemeters | 67 | 30 | Each |
|---|
| 68 | 68 | Splicing of one core of OF cable | 68 | 18 | Each |
|---|
| 69 | Total in Figures | | | | |
|---|