Engaging of mandays for dressing the damaged lawn/hedges
5
Development of acupressure walking track
Ls
1.00
Ls
40000.00
40000.00
h. Water body construction CC
6
Development of acupressure walking track
As per
4.12
Cmt
1080.00
4455.00
g. Black clay soil
7
Development of acupressure walking track
As per
4.12
Cmt
600.00
2475.00
f. Fine sand
8
Development of acupressure walking track
As per
15.00
Bag
400.00
6000.00
e. Shreaded wood/barks
9
Development of acupressure walking track
As per
4.12
Cmt
747.00
3081.38
d. Query chips 6mm
10
Development of acupressure walking track
As per
4.12
ton
2100.00
8662.50
c. Sagar Stone tennis ball size
11
Development of acupressure walking track
As per
4.12
Cmt
1433.91
5914.88
b. 10 MM Chips
12
Development of acupressure walking track
Approv. Rate
4.12
Cmt
1433.91
5914.88
Accupressure Material: A. Stone Metal HPG 20mm size
13
Development of acupressure walking track
Approv. Rate
85.00
Each
225.50
19167.50
Cost, supply & fixing of per cost A.C.C kerb with size 600mm x 375mm x 110mm semi bated at top in M30 gread including cost & conveyance to site & labour charges for laying true to alignment & pointing with cement mortat in (1:3) prop
14
Development of acupressure walking track
GHMC U.R 3.14
14.85
Cmt
137.00
2034.45
Carting of debris including excavation, loading, unloading and transport upto a lead o 10 kms 99 Sqmts X 0.15 = 14.85 Cmt
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.